How to Fill Out Michigan EGLE Air Permit to Install (PTI) + FAQs

The Michigan EGLE Air Permit to Install (PTI) is the state air permit every person must obtain before installing, constructing, reconstructing, relocating, or modifying any process or process equipment that may emit air contaminants, unless a specific exemption applies under Rule 201 of the Michigan Air Pollution Control Rules. The permit is issued by the Air Quality Division (AQD) of the Michigan Department of Environment, Great Lakes, and Energy (EGLE) under Part 55 of the Natural Resources and Environmental Protection Act, 1994 PA 451.

Installing equipment without a required PTI is one of the most expensive mistakes a Michigan facility can make. EGLE’s enforcement record shows that civil fines for unpermitted construction can reach $10,000 per day, per violation, and AQD has issued thousands of PTIs since the program’s modernization in 2024 when applications moved into the MiEnviro Portal. This guide walks you through the application — Form EQP 5733 — line by line, in plain English.

Here is what you will learn:

  • 📝 How to complete every field on EGLE Form EQP 5733 and its supplements
  • 📂 Which supporting documents AQD demands before it will accept your package
  • 💻 How to file through the MiEnviro Portal step by step
  • 💵 How fees, deadlines, and the 18-month “commence construction” clock work
  • ⚖️ Which mistakes trigger denial, public hearings, or enforcement action

What the PTI Is and Who Must File It

A Permit to Install (PTI) is Michigan’s pre-construction air permit. It authorizes a person to install, build, alter, or relocate a process, fuel-burning unit, refuse-burning unit, or control device that emits or may emit any air contaminant. The legal anchor is Rule 336.1201, commonly called Rule 201, paired with Part 55 of NREPA, MCL 324.5501 et seq. The permit is not an operating permit. Operating authority for major sources comes later through the Renewable Operating Permit (ROP) program.

The form applies to a wide range of filers. Small businesses installing a single spray booth, mid-size manufacturers adding a 15 MMBtu/hr boiler, foundries adding a baghouse-controlled cupola, landfills adding flares, and gas stations replacing dispensers all fall under the same framework. The EGLE PTI program page lists more than two dozen exemptions in Rules 278 through 291, but if no exemption fits, the PTI is mandatory before any equipment is bolted to a slab.

Federal law overlays the state program. Major sources that trigger Prevention of Significant Deterioration (PSD) or Nonattainment New Source Review (NNSR) thresholds under the federal Clean Air Act must satisfy both Michigan PTI rules and federal NSR rules through the same application. Facilities that wish to stay below Title V applicability can use the synthetic minor “opt-out” PTI to accept federally enforceable limits. The current PTI application forms and supplements are listed on EGLE’s PTI guidance page, and the package as a whole is known in MiEnviro as the PTI Submission Package.


Before You Start: Documents and Information You Need

Open the form too early and you will stall halfway through. The application asks for plant-wide data, equipment specifications, and emission calculations that take days — sometimes weeks — to compile. The Michigan Guide to Air Use Permits to Install is the AQD’s foundational handbook and previews everything the form will ask.

Gather these items first:

  1. State Registration Number (SRN). Every facility tracked by AQD has a five-character SRN. If your site is new, you will request one inside MiEnviro. Without the SRN, AQD cannot route your package to the right district office.
  2. Legal entity information. You need the exact registered name of the company, federal EIN, and Michigan LARA entity ID. A typo here can void the permit at issuance.
  3. Site plot plan and process flow diagram. AQD wants to see where each emission unit sits on the property and how material moves through the process. Missing diagrams are the single most common cause of completeness rejections.
  4. Equipment specifications. Manufacturer cut sheets, heat input ratings, stack dimensions, flow rates, and control device design data are required for every emission unit.
  5. Emission calculations. Both potential to emit (PTE) and uncontrolled emissions must be calculated for each criteria pollutant (PM, PM10, PM2.5, SO2, NOx, CO, VOC, lead) and for any hazardous air pollutants (HAPs) listed under Section 112(b) of the Clean Air Act.
  6. Safety Data Sheets (SDS). Every coating, solvent, fuel, or feedstock referenced in the application needs a current SDS attached.
  7. BACT / T-BACT analysis. Best Available Control Technology for criteria pollutants and Toxic-BACT for air toxics must be documented under Rule 224 and Rules 702/705.
  8. Air dispersion modeling. AERMOD output is required when potential impacts exceed screening thresholds, especially for air toxics. The AQD modeling guidance lists the inputs AQD will accept.
  9. Public participation determination. Some permits trigger mandatory public notice and hearing under Rule 214a. You need to know in advance if your project qualifies.
  10. Fee payment authority. The permit fee — base plus per-emission-unit surcharges — must be paid through MiEnviro before the package is considered complete.

Where to Get the Form and How to Access It

All current PTI forms live on the EGLE PTI Application Forms & Instructions page. The core application is EQP 5733, General Permit to Install Application, and it is paired with supplemental forms numbered EQP 5734 through EQP 5742 that cover process emission units, boilers, generators, storage tanks, surface coating lines, and the new Equipment Inventory Form introduced in 2024.

Since December 16, 2024, AQD requires electronic submittal through the MiEnviro Portal. MiEnviro replaced the old paper and email submittals and is described by AQD as the consolidated platform for “notification, permitting, emissions reporting, and compliance.” The transition was announced in the AQD go-live bulletin of November 18, 2024. The portal organizes the application as a PTI Submission Package with built-in forms, attachment slots, and a certifier signature workflow.

To access the portal you need a free account. A “responsible official” must hold certifier rights so the application can be electronically signed. AQD also accepts a pre-application meeting request through MiEnviro — a step strongly recommended for any modification involving modeling, BACT, or PSD. If you cannot file electronically because of a documented hardship, contact the AQD Permit Section at 517-284-6700 for a paper waiver.


Step-by-Step: How to Fill Out EGLE Form EQP 5733 Line by Line

The general application (EQP 5733, current revision is the 2024 MiEnviro edition) is organized into eight major parts. Inside MiEnviro the parts appear as separate screens, but the field names match the PDF form exactly. Use the field names below verbatim — paraphrasing them is a common cause of rejection.

Part A, Box 1: Company / Source Name

Plain English. This field asks for the legal name of the company that will own and operate the equipment.

How to answer. Enter the exact name on file with Michigan LARA, in all capital letters, with no abbreviations.

Example. MIDWEST METAL FINISHING, LLC writes its name exactly that way, matching its LARA filing.

Nuance. If a parent corporation owns the site but a subsidiary operates it, list the operator as the source name and disclose the parent in Part B.

Common mistake and consequence. Using a “doing business as” name instead of the registered legal name causes the permit to be issued to a non-existent entity, which voids enforceability and triggers reissuance fees.

Misconception. Many filers think the trade name on the building sign is acceptable. AQD cross-checks against LARA, not signage.

Part A, Box 2: State Registration Number (SRN)

Plain English. Your facility’s unique five-character AQD identifier.

How to answer. Enter the SRN in the format issued by AQD, for example B1234. New sites should leave this blank and request an SRN inside MiEnviro.

Example. Aisha’s Auto Body, LLC uses SRN N4421 on every page of its package.

Nuance. Some companies operate multiple SRNs at one address — each “stationary source” gets its own SRN under Rule 116.

Common mistake and consequence. Submitting under the wrong SRN routes the package to the wrong district office and delays completeness review by 30 to 60 days.

Misconception. Filers believe a federal EIN substitutes for the SRN. It does not.

Part A, Box 3: Facility Physical Address

Plain English. Where the equipment will physically sit.

How to answer. Enter the street address, city, ZIP, and county where construction will occur.

Example. Carlos’s Foundry enters 812 Industrial Drive, Saginaw, MI 48601, Saginaw County.

Nuance. For mobile sources, such as portable nonmetallic mineral crushers, list the home base address and request a relocation provision under the General PTI for Crushers.

Common mistake and consequence. Listing a corporate headquarters instead of the construction site causes EGLE’s modeling staff to use wrong meteorological data, invalidating dispersion results.

Misconception. PO boxes are not acceptable in Box 3. They are only acceptable in the mailing address field of Part B.

Part A, Box 4: Permit Type Selection

Plain English. Tells AQD which permit pathway you are using.

How to answer. Check one of: Standard PTI, General Permit, Opt-Out (Synthetic Minor) PTI, PSD, or Nonattainment NSR.

Example. A small spray booth filer checks Standard PTI. A landfill flare project that triggers PSD checks PSD.

Nuance. A facility may file an opt-out simultaneously with a standard PTI when accepting federally enforceable limits to stay below Title V thresholds.

Common mistake and consequence. Checking Standard PTI when the project triggers PSD strips federal protections and may require restarting the public participation process under 40 CFR 51.166.

Misconception. Filers assume General Permits are always faster. They are only available for narrow equipment categories listed by AQD.

Part B: Responsible Official Contact

Plain English. The person legally accountable for the application’s content.

How to answer. Enter full legal name, title, phone, and email. The responsible official must meet the definition in Rule 211 — typically a corporate officer, plant manager with delegated authority, or owner.

Example. Janet Reyes, Vice President of Operations signs as the responsible official for the boiler installation.

Nuance. A consultant cannot serve as the responsible official, even with a power of attorney. Consultants are listed in Part C as the technical contact.

Common mistake and consequence. Listing the environmental coordinator without delegated signing authority makes the certification invalid and forces resubmittal.

Misconception. Many think the responsible official only needs to sign. They are personally certifying the truth of every emission calculation in the package.

Part C: Technical / Consultant Contact

Plain English. The person AQD will call with technical questions.

How to answer. Enter the consultant or in-house engineer who prepared the calculations, including firm name, phone, and email.

Example. Marcus Liu, P.E., Great Lakes Environmental Consulting is listed for the foundry application.

Nuance. If multiple consultants prepared different sections, list the lead and note others on the cover letter.

Common mistake and consequence. Leaving Part C blank delays review because AQD has no one to ask about emission factors.

Misconception. Filers think this contact is informal. AQD documents every conversation with the technical contact in the permit file.

Part D: Project Description

Plain English. A short narrative of what you are installing.

How to answer. Write two to five sentences describing the equipment, capacity, intended use, and any control devices.

Example. Midwest Metal Finishing is installing one 20-foot downdraft spray booth controlled by a three-stage particulate filter, with maximum coating usage of 50 gallons per day.

Nuance. Include the projected commence-construction date because the permit, once issued, requires construction to start within 18 months under Rule 201(6).

Common mistake and consequence. Vague descriptions cause AQD to issue narrow permit conditions that block future operational flexibility.

Misconception. Filers think the project description is marketing copy. It becomes part of the enforceable permit and limits how the equipment can be operated.

Part E: Emission Unit Table and Equipment Inventory Form

Plain English. A list of every emission unit covered by the application.

How to answer. For each unit enter the AQD Emission Unit ID (EUID), description, manufacturer, model, capacity, control device, and stack ID. The new Equipment Inventory Form introduced with MiEnviro for Air must accompany this part, as covered in the AQD MiEnviro webinar series.

Example. Carlos enters EUCUPOLA01, 5-ton coke-fired cupola, Whiting Equipment, 1995, controlled by BAGHOUSE01, stack SVCUPOLA01.

Nuance. Group similar small units (for example, identical generators) only when allowed by Rule 287 flex provisions. Otherwise list each one separately.

Common mistake and consequence. Reusing EUID numbers from old permits without confirming with AQD creates database conflicts and forces manual reconciliation.

Misconception. Filers think exempt units do not belong here. Exempt-but-installed units must still be listed in the facility-wide Equipment Inventory.

Part F: Emission Calculations

Plain English. The numbers that prove your project will not violate any limit.

How to answer. Provide pollutant-by-pollutant calculations for both uncontrolled and potential to emit. Use AP-42 emission factors, stack test data, or manufacturer guarantees, and cite the source for each number. The EPA AP-42 compilation is the default reference.

Example. Janet’s 15 MMBtu/hr natural gas boiler shows NOx PTE of 9.86 tons/year using AP-42 Section 1.4 factor of 100 lb/MMscf and 8,760 hours of operation.

Nuance. PTE must assume continuous operation at maximum rated capacity, with no credit for control devices unless the control is federally enforceable.

Common mistake and consequence. Taking control credit without proposing a federally enforceable limit causes AQD to recalculate PTE without the control, often pushing the project into PSD.

Misconception. Filers believe annual hours can be limited informally. Only an enforceable hours-of-operation condition reduces PTE.

Part G: BACT, T-BACT, and Air Quality Analysis

Plain English. Your justification for the control technology you chose.

How to answer. For each significant emission unit, document the top-down BACT analysis: identify available controls, eliminate technically infeasible ones, rank the remainder by effectiveness, and justify the selection on cost, energy, and environmental grounds. For air toxics, perform a T-BACT analysis under Rules 224, 225, and 228.

Example. Marcus’s foundry selects a baghouse with 99.5% PM control after eliminating wet scrubbers on energy grounds.

Nuance. AQD compares your BACT analysis to the RBLC database — if you propose less stringent controls than recent comparable permits, expect pushback.

Common mistake and consequence. Skipping the cost-per-ton calculation makes the BACT analysis incomplete and stops the technical review clock.

Misconception. Filers think BACT means “best you can afford.” It means “best demonstrated technology” unless cost is shown to be disproportionate.

Part H: Modeling Demonstration

Plain English. Air dispersion modeling that shows ambient impacts comply with National Ambient Air Quality Standards and Michigan toxic screening levels.

How to answer. Submit AERMOD inputs, source parameters, meteorological data, receptor grid, and output tables. AQD’s air modeling guidance explains accepted protocols.

Example. Janet’s boiler modeling shows max 1-hour NO2 impact of 95 µg/m³, below the 188 µg/m³ NAAQS.

Nuance. Some projects qualify for the AQD screening tool, but anything with toxics above the initial threshold screening level (ITSL) requires refined AERMOD runs.

Common mistake and consequence. Using default urban dispersion coefficients on a rural site overestimates dispersion and may pass modeling that should fail, leading to permit reopening.

Misconception. Filers think modeling is optional for small sources. It is required whenever AQD’s screening thresholds are exceeded, regardless of size.

Part I: Certification and Signature

Plain English. The legal oath that everything in the package is true.

How to answer. The responsible official identified in Part B signs electronically through MiEnviro using their certifier credentials.

Example. Janet Reyes clicks Certify and Submit, generating a tamper-evident signature block stored in the permit file.

Nuance. The signature carries criminal penalties for false statements under MCL 324.5531.

Common mistake and consequence. Letting a consultant sign with a shared login violates the certification rules and can void the permit.

Misconception. Filers think a wet-ink signed PDF is acceptable. Since December 2024, MiEnviro electronic certification is the required method except under documented hardship waivers.


Three Filled-Out Examples Using Real Scenarios

Scenario 1: Aisha’s Auto Body Shop Installing a Spray Booth

Form Section What Aisha Enters
Source Name AISHA’S AUTO BODY, LLC
SRN N4421
Facility Address 512 Main Street, Lansing, MI 48910, Ingham County
Permit Type Standard PTI
Responsible Official Aisha Johnson, Owner
Project Description Install one 14-foot crossdraft spray booth with three-stage particulate filter, max 20 gallons coating per day
Emission Unit Table EUBOOTH01, Global Finishing 14-ft booth, FILTER01, stack SVBOOTH01
Emission Calculations VOC PTE 4.8 tpy, HAPs PTE 0.9 tpy combined
BACT HVLP spray guns + three-stage filters, justified vs. waterborne coatings
Certification Aisha certifies electronically in MiEnviro

Scenario 2: Janet’s Manufacturing Plant Adding a 15 MMBtu/hr Boiler

Form Section What Janet Enters
Source Name NORTHERN PRECISION MANUFACTURING, INC.
SRN B2210
Facility Address 1400 Industrial Park, Grand Rapids, MI 49504, Kent County
Permit Type Standard PTI with synthetic minor opt-out
Responsible Official Janet Reyes, VP Operations
Project Description Install one 15 MMBtu/hr natural gas-fired firetube boiler with low-NOx burner
Emission Unit Table EUBOILER02, Cleaver-Brooks CBLE-700, low-NOx burner, stack SVBOILER02
Emission Calculations NOx PTE 9.86 tpy, CO PTE 7.4 tpy, PM PTE 0.6 tpy
BACT / Modeling Low-NOx burner + flue gas recirculation; AERMOD shows max 1-hr NO2 of 95 µg/m³
Opt-Out Limits Accept facility-wide NOx limit of 90 tpy to stay below Title V

Scenario 3: Carlos’s Foundry Adding a Baghouse-Controlled Cupola

Form Section What Carlos Enters
Source Name GREAT LAKES FOUNDRY, LLC
SRN A1057
Facility Address 812 Industrial Drive, Saginaw, MI 48601, Saginaw County
Permit Type Standard PTI
Responsible Official Carlos Mendez, Plant Manager
Project Description Install one 5-ton coke-fired cupola controlled by pulse-jet baghouse
Emission Unit Table EUCUPOLA01, Whiting 5-ton cupola, BAGHOUSE01 with 99.5% PM control, stack SVCUPOLA01
Emission Calculations PM PTE 12.3 tpy controlled, CO PTE 145 tpy, lead PTE 0.04 tpy
BACT and T-BACT Baghouse selected after wet scrubber eliminated for energy; lead T-BACT met
Modeling AERMOD shows lead 3-month avg 0.08 µg/m³, below NAAQS

How to File the Completed Form

EGLE accepts PTI submittals through three channels, but MiEnviro Portal is now the default.

MiEnviro Portal (online). Log into MiEnviro, open Start a New Submission, choose PTI Submission Package, complete every screen, upload attachments, pay the fee with credit card or ACH, and certify. Expected completeness review is 30 days; technical review for a standard PTI is generally 120 to 180 days from the completeness determination. AQD emails a submittal confirmation that should be saved as proof of filing.

Paper waiver submittal. For filers granted an electronic submittal waiver, the address is EGLE, Air Quality Division, Permit Section, P.O. Box 30260, Lansing, Michigan 48909-7760, the same address used for written comments listed on the AQD public notice page. Mail the original signed application plus one paper copy and a check made payable to State of Michigan. Keep the certified mail green card as proof of filing.

Pre-application meeting. This is not a filing channel but is strongly recommended. Request the meeting inside MiEnviro at least 30 days before submittal; AQD modeling and permit engineers will review draft calculations and flag deficiencies before the formal clock starts.

Fees follow Part 55 and are published annually by EGLE. As of fiscal year 2026 the base PTI fee is roughly $1,500, with per-emission-unit surcharges that scale with complexity and a separate fee for opt-out and PSD permits. PSD applications can cost more than $15,000 when fully assessed. Unpaid fees accrue penalties as described in the Michigan Guide to Air Use Permits.


What Happens After You File

AQD reviews the package in two stages. The first 30 days are a completeness review: staff confirm every required form, attachment, calculation, and fee are present. If anything is missing, AQD issues a deficiency letter and the application is paused until the gap is filled.

The second stage is technical review. Engineers analyze emission calculations, BACT, T-BACT, modeling, and applicable federal requirements. They will issue informal comments — sometimes multiple rounds — and may schedule conference calls. Once technical review is complete AQD drafts proposed permit terms.

For projects that meet thresholds in Rule 214a, a 30-day public comment period is held, with optional public hearing. Examples are visible on the AQD’s running public notice list. After public input, AQD issues a final decision: approval, conditional approval, or denial. Approved permits give the holder 18 months to commence construction under Rule 201(6); failure to start within that window voids the permit and forces reapplication.


Mistakes to Avoid When Filling Out the Form

  1. Skipping the pre-application meeting. Consequence: missed modeling triggers and avoidable BACT revisions during technical review.
  2. Using the trade name instead of the LARA legal name. Consequence: permit is issued to a non-existent entity and must be reissued.
  3. Leaving Box 2 (SRN) blank when one already exists. Consequence: package routed to wrong district office.
  4. Calculating PTE with informal hours limits. Consequence: AQD recalculates without the limit, often pushing project into PSD.
  5. Taking control credit without proposing federally enforceable conditions. Consequence: PTE recalculated, triggering Title V applicability.
  6. Missing the Equipment Inventory Form. Consequence: package rejected as incomplete under MiEnviro intake rules.
  7. Citing outdated AP-42 emission factors. Consequence: technical reviewer requests recalculation, delaying review by weeks.
  8. Skipping T-BACT for air toxics. Consequence: violation of Rule 225 and possible denial.
  9. Using default urban dispersion modeling on a rural site. Consequence: overestimated dispersion, leading to permit reopening when the error is discovered.
  10. Vague project description. Consequence: narrow enforceable terms that restrict future flexibility.
  11. Listing a consultant as the responsible official. Consequence: invalid certification and forced resubmittal.
  12. Forgetting to pay the fee in MiEnviro. Consequence: package remains in “draft” status indefinitely.

Do’s and Don’ts

Do request a pre-application meeting for any project with modeling, BACT, or PSD implications because AQD will preview issues for free.

Do match every field name to the exact wording on EQP 5733 because AQD’s database matches field names to enforceable terms.

Do itemize HAPs separately from VOC totals because HAP thresholds drive Title V applicability independently.

Do keep your MiEnviro confirmation email forever because it is your only proof of filing date.

Do document every BACT cost calculation in dollars per ton because AQD will reject hand-waved economic infeasibility claims.

Do include a clear plot plan because reviewers use it to confirm setbacks and modeling receptor placement.

Don’t install equipment before the permit is issued because Rule 201 prohibits it and penalties reach $10,000 per day.

Don’t assume an exemption applies without confirming the exact rule citation because misapplied exemptions are a leading enforcement target.

Don’t copy emission calculations from old permits without verifying the emission factors because AP-42 factors are updated frequently.

Don’t wait for the 18-month construction clock to expire because reapplication restarts the entire review.

Don’t treat the technical contact line as optional because reviewers will not chase down phone numbers.

Don’t submit modeling without electronic input files because AQD modelers must re-run your scenario to certify it.


Pros and Cons of Filing on Your Own vs. With Help

Pros of filing yourself.

  • You save consultant fees, which often range from $10,000 to $50,000 for a standard PTI.
  • You build institutional knowledge of your own equipment and emission factors.
  • You control the schedule and can respond quickly to AQD comments.
  • You learn MiEnviro firsthand, which speeds future renewals and modifications.
  • You avoid miscommunication that often happens when a third party drafts the narrative.

Cons of filing yourself.

  • BACT and modeling demands rise sharply for medium and large sources.
  • AQD will not draft narrative for you; gaps cost months.
  • Federal PSD/NNSR overlay rules are technical and unforgiving.
  • A single error in PTE can trigger Title V applicability for years.
  • Public hearings require legal and technical preparation that goes beyond the form itself.

Standard PTI vs. Opt-Out (Synthetic Minor) PTI

Feature Standard PTI Opt-Out PTI
Purpose Authorize installation Authorize installation and keep facility below Title V
Federal enforceability Optional Required
Public participation Triggered by Rule 214a thresholds Always required for new opt-outs
Typical review time 120–180 days 150–210 days
Typical fee Base + per-EU Higher base + per-EU

FAQs

Do I need a PTI if I am only replacing identical equipment?

No. Like-kind replacement of identical equipment with no emission increase generally falls under Rule 285(2)(a), but you must confirm the exemption applies before installation.

Can I file the PTI application by email?

No. Since December 16, 2024, EGLE requires electronic submittal through MiEnviro Portal, with paper accepted only under a documented hardship waiver from the AQD Permit Section.

What is the State Registration Number in Box 2?

Yes, it matters — the SRN is your facility’s five-character AQD identifier, and a wrong or missing SRN in Box 2 routes the package to the wrong district office, causing weeks of delay.

Do I write the parent company or operator in the Source Name box?

No. Box 1 asks for the operator’s legal name as registered with Michigan LARA; the parent entity is disclosed separately in Part B.

Can my consultant sign Part I as responsible official?

No. Rule 211 requires a corporate officer, owner, or duly authorized plant manager — never a consultant — to sign the certification.

Do I need to list exempt emission units on the Equipment Inventory Form?

Yes. The Equipment Inventory Form requires a full facility-wide list including exempt units so AQD’s database reflects every emission source on site.

Is BACT required for every emission unit?

No, BACT applies to significant new or modified units; small or trivial sources may use simplified justifications, but T-BACT under Rule 225 still applies for air toxics.

How long do I have to commence construction after permit issuance?

Yes, there is a hard deadline — Rule 201(6) gives you 18 months from the issuance date to begin actual on-site construction or the permit is void.

Do I have to do air dispersion modeling for a small boiler?

No, not always — small boilers below AQD screening thresholds are exempt from refined modeling, but anything that exceeds an ITSL for air toxics triggers AERMOD modeling.

Can I install first and apply later under a “grandfather” rule?

No. Michigan has no general grandfather provision for new construction; installing before issuance violates Rule 201 and exposes the company to penalties up to $10,000 per day.

Are PTI applications subject to public comment?

Yes, when Rule 214a thresholds are met or when the project is a synthetic minor opt-out, public notice and a 30-day comment period are mandatory.

What is the difference between PTE and actual emissions on the form?

Yes, the difference matters — PTE assumes maximum capacity for 8,760 hours per year unless federally enforceable limits reduce it, while actual emissions are not used for applicability determinations.

Can I appeal an AQD permit denial?

Yes. Denials may be contested by filing a petition with the Michigan Office of Administrative Hearings and Rules within 60 days of the final decision.

Do I include Safety Data Sheets for every coating?

Yes. Current SDSs for each coating, solvent, fuel, or feedstock are required attachments and missing SDSs are a top-five completeness rejection reason.

Does the PTI authorize me to operate the equipment forever?

No. The PTI authorizes installation and initial operation; major sources later move into Renewable Operating Permits, and minor sources continue to operate under the PTI subject to its conditions.