How to Fill Out Ohio EPA Solid Waste Permit Application (w/Examples) + FAQs

The Ohio EPA Solid Waste Permit to Install (PTI) application is the form you submit to the Ohio Environmental Protection Agency before you build, expand, or change a solid waste facility such as a transfer station or a municipal solid waste landfill. You must get this permit approved before you put a shovel in the ground, and the rules behind it come from Ohio Revised Code Chapter 3734 and the rules in Ohio Administrative Code 3745-27-02.

This guide walks you through the Solid Waste Transfer Facility PTI Application (Guidance Document #698) line by line, and it points out where the Municipal Solid Waste Landfill PTI form differs. The form looks short at five pages, yet a single missing signature or wrong fee can stall your project for months. About one in three solid waste PTI applications gets a deficiency letter on the first pass, which can add 60 to 90 days to a timeline that often runs a year or more.

Here is what you will learn in this guide:

  • 📋 What each box on the five-page PTI form asks and how to answer it
  • 💵 The exact fees, where to send them, and when the balance is due
  • 🏗️ Three full filled-out examples for a new transfer station, a landfill expansion, and a call-in
  • ⚠️ The field-level mistakes that trigger deficiency letters and denials
  • ✅ A do’s and don’ts list plus 12 plain-answer FAQs to close the gaps

What the Form Is and Who Must File It

The Solid Waste PTI application is a request for Ohio EPA’s Division of Materials and Waste Management (DMWM) to approve the siting, design, construction, monitoring, and operation of a new or changed solid waste facility. Under ORC 3734.05, no person may establish or modify a solid waste facility without first obtaining this permit from the director of Ohio EPA. The permit is the gatekeeper that proves your facility meets Ohio’s environmental standards before it ever opens.

You must file this form if you plan to build a new transfer facility, build a new landfill, expand an existing one, or change how an existing facility receives or handles waste. A transfer facility is a site used mainly to move solid waste from one vehicle or container into another for transport to a disposal site, and per Ohio EPA guidance, new transfer facilities and modifications both require a PTI. Legitimate recycling facilities do not need this permit, which is a common point of confusion.

The form is split into three sections. Section 1 collects facility, applicant, owner, operator, and preparer information plus the certification signature. Section 2 covers the reason for the application, variances, the applicant’s meeting, facility size, and waste types. Section 3, called Multimedia Information, asks about other Ohio EPA permits you may need from the Division of Surface Water and the Division of Air Pollution Control.

The PTI is only the first license in a chain. After Ohio EPA issues the PTI, a transfer facility owner must still get an annual operating license from the local health district before opening, and transfer facilities are inspected quarterly by the licensing authority. Skipping the PTI step and building anyway can lead to enforcement action under ORC Chapter 3734, including orders to stop work and civil penalties.

Before You Start: Documents and Information You Need

Gather these items before you open the form. A missing piece is the top reason an application sits in a deficiency loop.

  • The facility’s exact legal name, street address, county, and the latitude and longitude of the center of the facility, because Ohio EPA maps every site and a wrong coordinate can misroute your file to the wrong district office.
  • The applicant’s full contact information, since this is the party Ohio EPA writes to for every deficiency letter and missing this delays responses.
  • The property owner’s name and parcel number(s), because Ohio EPA confirms who holds title to the land and a mismatch raises a legal-standing question.
  • The operator’s information if it differs from the applicant, since the operator is the party with day-to-day control and the rules tie duties to that role.
  • The preparer’s information, usually the engineer or consultant, because Ohio EPA often contacts this person for technical questions.
  • The $400 nonrefundable application fee, made payable correctly, because the form is not complete without proof the fee is enclosed.
  • Total facility acreage and waste handling area in square feet, since these numbers drive the technical review and the permit fee.
  • The anticipated daily waste receipt and the types of waste you will accept, because these define the scope of your permit and your operating limits.
  • Records of any other Ohio EPA permits (NPDES surface water, air pollution control) so you can complete Section 3 accurately.
  • The planned date and location of your applicant’s public meeting, which ORC 3734.05 requires before the permit can issue.

For a landfill, you will also need engineering drawings sealed by a professional engineer, a hydrogeologic study, and a disclosure statement filed with the Ohio Attorney General’s Office for the background check. Missing any of these for a landfill almost guarantees a deficiency letter and a long delay.

Where to Get the Form and How to Access It

You download the official PTI forms from the Ohio EPA forms page under the heading “Permit-to-Install Application Forms.” The Transfer Facility PTI is published as Guidance Document #698, and the Municipal Solid Waste Landfill PTI is Guidance Document #696. Always download a fresh copy each time you file, because Ohio EPA updates forms and an old version may miss required fields.

The form is a fillable PDF you can type into on a computer, which is the cleaner method, or print and complete by hand in black ink. The five pages are labeled “Page 1 of 5” through “Page 5 of 5” in the footer, so check that you have all five before you start. The top of page 1 has an “Ohio EPA Use Only” box for the Secondary ID and Date Received, which you leave blank for the agency to fill.

You file the completed application with the Ohio EPA district office that covers your facility’s county, not with the central Columbus office by default. Ohio EPA runs five district offices: Central in Columbus, Northwest in Bowling Green, Southwest in Dayton, Northeast in Twinsburg, and Southeast in Logan. Sending the form to the wrong office adds days while staff reroute it, so confirm your county’s district before mailing.

Step-by-Step: How to Fill Out the Solid Waste Transfer Facility PTI Line by Line

The walkthrough below follows the form in order. Use the exact field labels printed on the form. Sample entries are shown in italics.

Section 1, Facility Information: Legal Name and Location

This block asks for the official name and physical location of the facility you want to build or change. Enter the Legal Name of the facility, then the Street Address, City, ZIP, County, and the Lat./Long./Center of Facility. The State field is pre-filled as Ohio. For example, Buckeye Transfer Station LLC, 4820 Industrial Parkway, Columbus, 43228, Franklin, 39.9612, -83.1408.

Write the legal name exactly as it appears on your business filings, not a nickname or a “doing business as” trade name, because Ohio EPA cross-checks the name against the property and applicant records. A common edge case is a facility with no street address yet because it is undeveloped land; in that case use the parcel location and the nearest road with directions, and supply the coordinates. The most common mistake here is dropping or rounding the latitude and longitude, which can place your site in the wrong county and route the file to the wrong district office, costing weeks. Many filers believe the address can be approximate since the maps are attached anyway, but Ohio EPA treats the coordinates as the legal location of record.

Section 1, Applicant Information

The Applicant Information block asks who is asking for the permit. Enter the Applicant Name, Company, Mailing Address, City, State, ZIP, Phone Number, and Email Address. For example, Daniel Reyes, Buckeye Waste Holdings Inc., 100 Corporate Center Dr., Suite 400, Dublin, OH, 43017, (614) 555-0142, dreyes@buckeyewaste.com.

The applicant is the person or company that will hold the permit and carry legal responsibility for the facility, so name the entity, not just an employee, and add a contact person. A frequent edge case is when a parent company applies on behalf of a subsidiary; list the entity that will actually operate and hold the permit. The biggest mistake is giving an email that nobody checks, because every deficiency letter and meeting notice flows to that address, and a missed deficiency letter can let your application lapse. People often assume the applicant must be the landowner, but the applicant, owner, and operator can be three different parties, which the next blocks handle.

Section 1, Property Owner Information

This block asks who holds title to the land, and you complete it only if the owner differs from the applicant. The form states “The owner holds title to the land.” Enter the Property Owner Name, Parcel Number(s), Mailing Address, City, State, ZIP, Phone Number, and Email Address. For example, Franklin County Land Trust, parcel 010-123456, 200 Civic Way, Columbus, OH, 43215.

The parcel number is the key field here, because Ohio EPA and the county auditor use it to confirm the land’s legal description and ownership. If there are several parcels or several owners, the form tells you to “attach additional entries for each property owner as needed,” so do not cram them into one line. The common mistake is leaving this block blank when the applicant leases the land from someone else, which creates a gap Ohio EPA must resolve before review. Filers often think a lease makes them the owner for the form’s purpose, but you must still list the title holder.

Section 1, Operator Information

The Operator Information block asks who runs the facility day to day, completed only if the operator differs from the applicant. The form notes “The operator has supervisory authority over the facility.” Enter the Operator Name, Mailing Address, City, State, ZIP, Phone Number, and Email Address. For example, Midwest Transfer Operations LLC, 4820 Industrial Parkway, Columbus, OH, 43228.

The operator is the entity with hands-on supervisory control, and many compliance duties attach to this role, so name it accurately. A common edge case is a city that owns and applies for a facility but hires a private contractor to run it; the contractor goes here. The mistake to avoid is naming an operator who is not yet under contract, which can force an amendment later if the operator changes. Some applicants think listing an operator shifts all liability away from themselves, but the applicant still holds the permit and shares responsibility.

Section 1, Preparer Information

This block asks who actually prepared the application, usually an engineer or environmental consultant. Enter the Preparer Name, Company, Mailing Address, City, State, ZIP, Phone Number, and Email Address. For example, Karen Whitfield, P.E., Whitfield Environmental Consulting, 55 Tech Blvd., Worthington, OH, 43085, (614) 555-0188.

Ohio EPA contacts the preparer for technical questions about the drawings and calculations, so list the person who can actually answer them. A common edge case is an in-house engineer who is also an employee of the applicant; you still complete this block fully. The mistake to avoid is leaving the phone and email blank, because a reviewer with a quick question may issue a formal deficiency letter instead of making a call, slowing everything down. Filers sometimes think the preparer must be a licensed engineer for every facility, but the seal requirement applies to the engineering plans, not the contact block.

Section 1, Certification and Signature

The Certification block is where an authorized person swears the application is true and complete. The form limits who may sign: for a corporation, a principal executive officer at least at the vice-president level or a duly authorized representative responsible for the facility; for a partnership, a general partner; for a limited liability company, a manager or member responsible for operations; for a sole proprietorship, the owner; and for a government facility, the principal executive officer or ranking elected official. Enter the Printed Name, Title, Signature, and Date, and check the Application Fee Enclosed box. For example, Daniel Reyes, Vice President of Operations, signed, 06/15/2026, box checked.

The signature is a legal certification that every fact in the document is true to the best of the signer’s knowledge, so an unauthorized or unsigned form is treated as incomplete. A common edge case is an LLC with multiple members; pick the one responsible for the facility’s overall operation. The single most damaging mistake on the whole form is having a junior staffer or the consultant sign when they lack signing authority, which voids the certification and forces a refile. Many applicants believe their consultant can sign for them, but the consultant is the preparer, not an authorized signatory.

Section 2, Reason for Application

This block asks why you are filing, and you check all that apply from four boxes: New Facility; Change to the limits of waste handling area; Call-in, ORC 3734.05(A)(3); and Change in technique of waste receipt or type of waste received. For example, a brand-new transfer station checks only New Facility, while an existing site adding a tipping bay checks Change to the limits of waste handling area.

Your choice here tells Ohio EPA how deep the review must go and whether public meetings are required. A common edge case is a facility making two changes at once, such as expanding the handling area and accepting a new waste type; check both boxes. The mistake to avoid is checking “New Facility” for what is really a modification, which can attach the wrong review track and fees. A “call-in” is a special case where Ohio EPA orders an existing facility to apply, and filers often confuse it with a voluntary modification, so only check that box if the agency directed you to apply.

Section 2, Variances, Exemptions, Alternatives

This block asks whether you are requesting any departure from the standard rules, listed in a table with three columns: Variance, Exemption, or Alternative; Citation; and Description. Enter the type, the rule citation, and a short description for each request. For example, Alternative, OAC 3745-555-xxx, use of a paved drive-over scale in place of a standard pit scale.

You name the exact rule you want relief from and explain what you propose instead, because Ohio EPA evaluates each request on its technical merit. A common edge case is having no variances at all, in which case you leave the table blank or write “None.” The mistake to avoid is hiding a design that does not meet a rule instead of requesting a formal variance, because Ohio EPA will catch it in review and treat the omission as a deficiency. Filers often think a variance is automatic if it sounds reasonable, but each one must be justified and approved.

Section 2, Applicant’s Meeting

This block captures the public meeting that ORC 3734.05 requires, with two fields: Location and Anticipated Date. Enter where and when you will hold the meeting. For example, Columbus Public Library, Hilltop Branch, 07/30/2026.

The applicant’s meeting lets the public ask questions about your facility, and per Ohio EPA guidance it must happen no later than 45 days after you submit the application, with a newspaper notice published at least 30 days before. A common edge case is a minor modification that may not require a meeting; confirm with your district office before leaving it blank. The mistake to avoid is scheduling the meeting too late or skipping the 30-day notice, which invalidates the meeting and forces you to redo it. Applicants often think they can hold the meeting after Ohio EPA finishes its review, but the timing is fixed by statute.

Section 2, Licensing Authority, Domicile, and Facility Size

This grouped block asks for the Licensing Authority (Ohio EPA or an approved local Board of Health), the Nearest Domicile not owned by the applicant with the owner’s name and distance, and the Facility Size in acres broken into Total Facility Area, Area Owned by Applicant, Area Leased by Applicant, and Area, Other with an explanation. For example, licensing authority Franklin County Public Health, nearest domicile J. Carter, 0.4 miles, total area 6.5 acres, owned 6.5, leased 0.

These numbers set the physical footprint of your permit and confirm setbacks from homes. A common edge case is land held under mixed tenure, where part is owned and part leased; split the acreage across the right lines and use the “Explain” field. The mistake to avoid is misstating the nearest domicile distance, since setback rules protect nearby residents and a wrong figure can sink the siting review. Filers sometimes assume the domicile field means the nearest building of any kind, but it means the nearest home not owned by the applicant.

Section 2, Waste Handling Area and Daily Receipt

This block asks for the Waste Handling Area Size in square feet, split into Total Waste Handling Area, Area Previously Approved, and New Area Added or Subtracted by this Permit, plus the Expected Daily Waste Receipt with Anticipated and Current figures. For example, total 18,000 sq ft, previously approved 0, new added 18,000, anticipated daily receipt 250 tons per day, current 0.

These figures define your operating limits and feed the technical and fee review. A common edge case is an expansion where some area was already approved; show the prior figure and the net change so the math is clear. The mistake to avoid is reporting the whole site area here instead of just the waste handling area, which inflates the numbers and confuses the reviewer. Filers often think “daily receipt” means yearly volume divided by 365, but it means the peak daily tonnage you expect to handle.

Section 2, Types of Waste to be Received

This block asks you to list each Type of Waste the facility will accept, with room to “attach additional entries as needed.” Enter each waste stream on its own line. For example, municipal solid waste, commercial solid waste, non-hazardous industrial solid waste.

The waste types you list become the legal scope of your permit, and you cannot lawfully accept a stream you did not name. A common edge case is wanting to keep options open; still list only the streams you can justify, because vague entries draw questions. The mistake to avoid is listing a waste your facility is not designed to handle, which can trigger added design requirements or a denial. Filers often believe they can add waste types informally later, but adding a new type usually requires a permit modification.

Section 3, Multimedia Information: Surface Water and Air

Section 3 asks whether you hold or need permits from other Ohio EPA divisions. Under Division of Surface Water, answer whether you have a Current NPDES Permit (Yes/No) with the permit number and dates, and whether a New/Modified DSW Permit Application is Required, Submitted, and Issued, with dates and numbers. Under Division of Air Pollution Control, answer the same set for Current DAPC Permit(s). For example, NPDES Yes, permit 4IN00123, issued 01/2024, new DSW application No, DAPC No.

This section coordinates your solid waste permit with stormwater and air permits so Ohio EPA can issue them together or in sequence. A common edge case is a facility that discharges stormwater and needs an NPDES permit it has not yet applied for; mark “Required: Yes, Submitted: No” honestly. The mistake to avoid is checking “No” to dodge a permit you actually need, because Ohio EPA reviews across divisions and will find the gap. Filers often think the solid waste PTI covers all environmental impacts, but air and water permits are separate authorizations.

Section 3, Other Authorizations

The final block lists any Other Authorization such as a license, other permits, or plan approvals, in a table with three columns: Other Authorization (including any reference number), Local, State, or Federal Office, and Date Applied For/Issue Date. For example, floodplain development permit #FP-22, City of Columbus, applied 05/2026.

This block gives Ohio EPA the full picture of every approval your project touches. A common edge case is a project in a floodplain or near a stream that needs a local or Army Corps approval; list it here. The mistake to avoid is omitting a known approval, which makes the application look incomplete and invites a deficiency letter. Filers often assume only Ohio EPA permits belong here, but local and federal authorizations count too.

Three Filled-Out Examples Using Real Scenarios

Below are three common fact patterns followed through the major sections of the form.

Scenario 1: Daniel Reyes Builds a New Transfer Station

Daniel files for a brand-new municipal solid waste transfer station in Franklin County.

Form Section What Daniel Enters
Legal Name Buckeye Transfer Station LLC
Lat./Long. 39.9612, -83.1408
Applicant Buckeye Waste Holdings Inc., Daniel Reyes
Property Owner Same as applicant, left blank
Operator Midwest Transfer Operations LLC
Certification Daniel Reyes, Vice President, signed 06/15/2026, fee box checked
Reason for Application New Facility checked
Applicant’s Meeting Hilltop Library, 07/30/2026
Waste Handling Area 18,000 sq ft new, 250 tons/day anticipated
Waste Types municipal solid waste, commercial solid waste
Section 3 NPDES Required: Yes, Submitted: No; DAPC No

Scenario 2: Janet Okafor Expands a Landfill

Janet, a compliance officer, files a landfill PTI to expand an existing municipal solid waste landfill by adding a new disposal cell.

Form Section What Janet Enters
Legal Name Valley View Sanitary Landfill
Reason for Application Change to the limits of waste handling area checked
Property Owner Valley View Land Co., parcel 045-998877
Operator Same as applicant, left blank
Variances Alternative liner design, OAC 3745-27, engineered gecomposite
Applicant’s Meeting County Fairgrounds Hall, 08/12/2026
Facility Size 140 acres total, 25 new acres this permit
Waste Handling Area Previously approved 60 acres, adding 12 acres
Waste Types municipal solid waste
Section 3 NPDES Yes, current; DAPC Yes, landfill gas permit current
Certification Janet Okafor, Authorized Representative, signed, fee enclosed

Scenario 3: Marcus Bell Responds to a Call-In

Marcus owns a small transfer facility that Ohio EPA ordered to apply for a PTI under ORC 3734.05(A)(3).

Form Section What Marcus Enters
Legal Name Bell Hauling Transfer Point
Applicant Bell Hauling LLC, Marcus Bell, sole member
Reason for Application Call-in, ORC 3734.05(A)(3) checked
Property Owner Marcus Bell (same as applicant, listed for clarity)
Operator Same as applicant, left blank
Nearest Domicile R. Patel, 0.3 miles
Waste Handling Area Total 9,500 sq ft, previously approved 9,500, net 0
Daily Receipt Current 80 tons/day, anticipated 80 tons/day
Waste Types municipal solid waste, construction debris
Certification Marcus Bell, Owner, signed, fee box checked

How to File the Completed Form

You file the completed PTI with the Ohio EPA district office for your facility’s county, along with the application fee and all attachments. The five district offices are: Central District, 50 W. Town St., Suite 700, Columbus, OH 43216-1049; Northwest District, 347 N. Dunbridge Rd., Bowling Green, OH 43402; Southwest District, 401 E. Fifth St., Dayton, OH 45402; Northeast District, 2110 E. Aurora Rd., Twinsburg, OH 44087; and Southeast District, 2195 Front St., Logan, OH 43138.

By mail, send the signed application, all attachments, and a check for the $400 nonrefundable application fee to the correct district office. The fee is set by ORC 3734.05(A)(2)(c) and ORC 3745.11(Q), and it is credited toward the permit fee if the permit issues. Make the check payable to “Treasurer, State of Ohio” and keep a copy of the check and your mailing receipt as proof of filing.

In person, you may hand-deliver the application package to your district office during business hours, which gives you a date-stamped copy on the spot. Ask the front desk to stamp your copy so you have dated proof of submission. This is useful when a statutory clock, such as the 45-day applicant’s meeting window, starts on the date received.

After the permit issues, the permit fee balance comes due. For a transfer facility the permit fee is $2,500, and the $2,500 balance (after the $400 credit is applied) is due within 30 days of PTI issuance. Processing time for a full review runs many months and often more than a year for landfills, because of public meetings, technical review, deficiency letters, and the public hearing, so file early and respond fast to any agency letter.

What Happens After You File

Ohio EPA publishes a legal notice that it received your application, appearing in its online Weekly Review and in a local newspaper. Staff then review the application for completeness and technical compliance, and if they find gaps they send you a deficiency letter requesting more information. You must answer deficiency letters promptly, because the review clock effectively pauses until you respond.

For new landfills, the Ohio Attorney General’s Office runs a background check on the applicant’s reliability, expertise, and competence before any permit can issue, and disqualifying criminal convictions can bar involvement in the business. Ohio EPA also holds a public information session to explain its review, with the applicant present to answer questions. The agency may not consider local zoning, out-of-state waste, truck traffic, or property values when deciding.

If the application meets the requirements, Ohio EPA issues a draft PTI, announces a public hearing, and opens a comment period of at least 30 days. After reviewing comments and preparing written responses, the director issues a final permit or requests more information. If the application falls short, Ohio EPA issues a proposed denial, which becomes final unless you request an adjudication hearing within 30 days.

A final permit or denial is an action of the director, and either may be appealed to the Environmental Review Appeals Commission within 30 days. You must also send a copy of the appeal to the director within three days of filing with ERAC. Further appeals can go through the courts.

Mistakes to Avoid When Filling Out the Form

  • Letting an unauthorized person sign the certification, which voids the certification and forces a refile.
  • Forgetting to check the “Application Fee Enclosed” box or omitting the $400 fee, which makes the application incomplete.
  • Mailing the form to the wrong district office, which delays processing while staff reroute it.
  • Entering wrong or rounded latitude and longitude, which can place the site in the wrong county.
  • Leaving the property owner block blank when the land is leased, which creates a legal-standing gap.
  • Checking “New Facility” for a modification, which attaches the wrong review track.
  • Scheduling the applicant’s meeting later than 45 days after filing, which invalidates the meeting.
  • Skipping the 30-day newspaper notice before the meeting, which forces you to redo the meeting.
  • Reporting total site area instead of waste handling area, which confuses the technical review.
  • Marking “No” in Section 3 for a water or air permit you actually need, which Ohio EPA catches across divisions.
  • Listing waste types your facility is not designed to handle, which can trigger denial or new design demands.
  • Hiding a non-conforming design instead of requesting a formal variance, which is treated as a deficiency.

Do’s and Don’ts

Do’s

  • Do download a fresh copy of the form each time, because Ohio EPA updates versions and old forms miss fields.
  • Do confirm your county’s district office before mailing, because the wrong office costs days.
  • Do have an authorized officer sign, because only listed roles may certify the application.
  • Do keep copies of the signed form, the check, and the mailing receipt, because they are your proof of filing.
  • Do answer deficiency letters fast, because the review clock pauses until you respond.
  • Do schedule the applicant’s meeting early, because the 45-day and 30-day notice rules are strict.

Don’ts

  • Don’t let a consultant sign the certification, because the preparer is not an authorized signatory.
  • Don’t guess the coordinates, because a wrong location misroutes the file.
  • Don’t omit the property owner when you lease the land, because Ohio EPA must confirm title.
  • Don’t understate the nearest domicile distance, because setback rules protect nearby homes.
  • Don’t list waste streams you cannot justify, because vague entries draw questions and delay.
  • Don’t assume the PTI covers air and water permits, because those are separate authorizations.

Pros and Cons of Filing on Your Own vs. With a Consultant

Filing Yourself (Pro Se) Filing With a Consultant or Engineer
Saves consultant fees, which matters for a small transfer site (pro) Costs added professional fees (con)
Full control over timing and content (pro) Engineer handles sealed plans and technical sections you may not (pro)
Risk of missing technical rules that draw deficiency letters (con) Lower risk of deficiency letters from experienced filers (pro)
Steep learning curve on ORC 3734 and OAC 3745 rules (con) Consultant knows district staff and current expectations (pro)
Works best for simple modifications (pro) Best for new landfills with complex hydrogeology (pro)
You may misjudge variance needs (con) Added cost may not pay off for a minor change (con)

Transfer Facility PTI vs. Landfill PTI

Solid Waste Transfer Facility PTI Municipal Solid Waste Landfill PTI
Five-page form, Guidance Document #698 Longer form with engineering attachments, Guidance Document #696
$400 application fee, $2,500 permit fee balance $400 application fee plus larger facility-based permit fees
Background check generally not the focus Attorney General background check required for new landfills
Quarterly inspections by licensing authority Extensive hydrogeologic and design review
Often a faster review Review commonly exceeds a year

FAQs

Do I have to file a PTI if I only run a recycling operation?

No. Ohio EPA does not require a permit or license for legitimate recycling facilities, so a true recycling operation does not file a solid waste PTI.

Can my environmental consultant sign the certification for me?

No. Only an authorized officer, general partner, LLC manager or member, sole proprietor, or ranking government official may sign; the consultant is listed as the preparer.

Do I leave the “Ohio EPA Use Only” box on page 1 blank?

Yes. The Secondary ID and Date Received fields are for agency staff, so you leave them empty for Ohio EPA to complete.

Should I fill in the Property Owner block if I own the land myself?

No. That block is completed only if the property owner differs from the applicant, though some filers list it for clarity.

Is the $400 application fee refundable if my permit is denied?

No. The application fee is nonrefundable, but if a permit issues, the $400 is credited against the permit fee due.

Do I write the total site acreage in the Waste Handling Area box?

No. The Waste Handling Area is reported in square feet and covers only the active handling area, not the whole site acreage.

Must I hold the applicant’s meeting before filing the form?

No. You file first, then hold the meeting no later than 45 days after submission, with a newspaper notice at least 30 days before.

Can I add a new waste type later without a new permit?

No. Adding a waste type your permit did not list usually requires a permit modification before you may accept that stream.

Do I check more than one box under Reason for Application?

Yes. The form says check all that apply, so a project making two changes at once checks both relevant boxes.

Is local zoning approval part of the Ohio EPA review?

No. Ohio law does not authorize Ohio EPA to consider local zoning; local officials enforce zoning codes separately.

Do I send the application to the Columbus central office?

No. You file with the district office that covers your facility’s county, unless that county falls under the Central District.

Can I appeal a denial of my PTI?

Yes. You may request an adjudication hearing within 30 days of a proposed denial, and appeal a final action to ERAC within 30 days.