How to Fill Out the Maryland MDE Air Quality Permit to Construct (Form 5) + FAQs

The Maryland Air Quality Permit to Construct is the one-time approval you must get from the Maryland Department of the Environment (MDE) before you build, install, modify, replace, or relocate any equipment that releases pollutants into the outside air. The main application is Form 5, filed with the Air and Radiation Administration (ARA) under the authority of COMAR 26.11.02 and Title 2, Subtitle 4 of the Maryland Environment Article.

If you start construction without this permit, you break state law and risk fines, a forced shutdown, and a denial that can stall your whole project. MDE warns that the most common cause of delay is an incomplete application, often a missing air toxics demonstration. According to MDE’s official permit guide, turnaround runs about 3 months for routine applications but can stretch to 11 months when a project draws heavy public interest.

Here is what you will learn in this guide:

  • ✅ Which MDE form fits your equipment and when Form 5 is the right choice.
  • 📋 Every document and number you must gather before you open the form.
  • ✍️ A line-by-line walkthrough of Form 5 with real example entries.
  • 🏭 Three full filled-out scenarios from a body shop, a printer, and a boiler install.
  • ⚠️ The field-level mistakes that get applications rejected and how to dodge them.

What the Form Is and Who Must File It

The Air Quality Permit to Construct is a pre-construction approval. It confirms that a new or changed source of air pollution will meet every air quality rule before the equipment goes in. The MDE permit guide states that any operation or equipment that discharges emissions to the outside air needs this permit. The agency that receives it is the Air and Radiation Administration (ARA), and the law behind it is COMAR 26.11.02.01 through .21, backed by Sections 110 and Title V of the federal Clean Air Act.

You must file if you plan to install, modify, replace, or move a source of air emissions. Common triggers include coating and painting operations, paint spray booths, asphalt plants, quarry operations, chemical-processing equipment, fuel-burning equipment, incinerators, and printing presses. The link between purpose, agency, statute, deadline, and penalty is simple: the statute (COMAR 26.11.02) requires the permit, the ARA reviews it, the project cannot begin until the permit issues, and building early exposes you to enforcement and possible removal of the equipment.

The “Permit to Construct” is really a family of forms, and picking the wrong one is a frequent first mistake. The MDE forms page explains that Form 5 covers all equipment except control devices, incinerators, and boilers. Below is how the core forms differ.

Form When You Use It
Form 5 General process and production equipment, spray booths, printing presses, and most other sources.
Form 5T Supplement to Form 5 or 10 to show T-BACT and ambient impact for toxic air pollutants under COMAR 26.11.15.
Form 5EP Supplement listing estimated toxic air pollutant emissions from each stack or emission point.
Form 6 Air pollution control devices, such as a baghouse or scrubber, usually filed with Form 5, 10, or 11.
Form 10 Municipal, industrial, medical waste, or sewage sludge incinerators (requires Forms 5T and 5EP).
Form 11 Fuel-burning equipment such as boilers (Forms 5T and 5EP not required).

A quick note on versions: as the MDE forms page notes, effective May 4, 2016, Form 5T replaced the old Form 5A and Form 5EP replaced Form 5B. Always download the current copy so your box numbers match this guide.

Before You Start: Documents and Information You Need

Gather everything before you open Form 5. MDE reviews each application for completeness first, and a missing item triggers a deficiency notice that pauses the clock. The MDE guide flags missing air toxics documentation as the top reason applications stall.

Here is your pre-filing checklist. Gather each item and know why it matters.

  • Legal company name and Federal Tax ID (FEIN). MDE ties the permit to a legal entity; a wrong name can force you to refile under the correct owner.
  • Facility (premises) address and mailing address. The premises address sets the air quality region and zoning; missing it stops the review.
  • Equipment make, model, and rated capacity. ARA cannot calculate emissions without the rated throughput or heat input, so a blank here guarantees a deficiency notice.
  • Process description and a process flow diagram. The diagram shows every emission point; without it, reviewers cannot confirm where pollution leaves the building.
  • Material data and usage rates. Coating gallons, fuel type, or raw material tons drive emission math; estimates without backup get rejected.
  • Safety Data Sheets (SDS) for coatings, solvents, and chemicals. These identify toxic air pollutants and feed the Form 5T and 5EP demonstration.
  • Emission estimates with calculation method. Show AP-42 factors, mass balance, or stack test data so MDE can verify your numbers.
  • Stack parameters. Height, diameter, exit temperature, and flow rate are needed for any ambient impact analysis.
  • Local zoning confirmation. For permits subject to public review, Section 2-404 requires proof of zoning compliance before MDE processes the application.
  • Control device details. If you add a baghouse, scrubber, or filter, you will need a Form 6 with its own specs.

Set aside time to call the Air Quality Permits Program at (410) 537-3225 or (410) 537-3230 if you are unsure which forms apply. A short pre-submittal conversation can save weeks.

Where to Get the Form and How to Access It

You can download Form 5 and every related form from the MDE Permits to Construct page in PDF format. The page also hosts Forms 5T, 5EP, 6, 10, 11, and the application checklist, which is now built into Forms 5, 10, 11, 41, 42, and 44.

You can also apply fully online. On May 28, 2026, MDE launched its new Environmental Service Center, where you can submit the application, pay fees electronically, and track status. The agency confirms on its Air Permits home page that General Permit, Permit to Construct, State Permit to Operate, and Title V applications can all be filed through this portal.

If you prefer a guided checklist, Maryland OneStop walks you to the same permit and lists the approval time and cost range. Whichever route you pick, download the form to your computer first and fill it with Adobe Acrobat Reader so your entries save correctly. For help, email MDE.Submit-AirPermits@maryland.gov or call (410) 537-3225.

Step-by-Step: How to Fill Out Form 5 Line by Line

Form 5 groups its questions into a company section, an equipment section, an emissions section, and a certification block. Work top to bottom, and never leave a box blank. If something does not apply, write N/A so MDE knows you did not skip it. The walkthrough below follows the order the items appear on the form.

Item 1: Applicant / Company Name

This field asks for the legal name of the business that will own or operate the equipment.

Enter the full legal name exactly as it appears on your state registration or tax records, in capital letters. For example, BAYSIDE AUTO BODY LLC writes its registered name, not a trade nickname. If your company uses a “doing business as” name, put the legal entity first and add the DBA in parentheses.

A common edge case is a parent company filing for a subsidiary; list the entity that will actually hold the permit, because the permit follows that legal owner. A frequent mistake here is using a brand or storefront name instead of the registered entity, which can void the permit or force a transfer later. Many filers think the name is just a label, but MDE cross-checks it against tax and zoning records, so a mismatch can stall the whole review.

Item 2: Facility (Premises) Address

This field asks where the equipment will physically sit.

Write the street address of the site, including city, county, and ZIP code, not your headquarters if they differ. For example, 1420 Pulaski Highway, Baltimore, Baltimore County, MD 21231 is a premises address. The county matters because it sets the applicable air quality region and any local zoning rules.

If the site has no street number yet, give the parcel ID, nearest intersection, or lot and block from the plat. The most common mistake is entering a P.O. Box or a billing address here, which breaks the zoning and regional analysis and triggers a deficiency notice. People often assume the mailing and premises address are the same, but MDE treats the premises as the regulated location, so always separate the two.

Item 3: Mailing Address and Contact Information

This field asks where MDE should send invoices, the permit, and any deficiency letters.

Provide a mailing address, a contact person, a phone number, and an email. For example, Maria Lopez, Plant Manager, P.O. Box 88, Baltimore, MD 21203, (410) 555-0142, maria.lopez@bayside.com. Name a real person who can answer technical questions fast.

If a consultant prepares the application, you can list them as the contact but the company stays the legal applicant. A common mistake is giving an address or email no one checks, which means you miss the fee invoice and the application sits frozen. Filers often think MDE will call if anything is wrong, but most deficiency notices arrive by mail or email, so a bad contact can quietly kill your timeline.

Item 4: Federal Tax Identification Number (FEIN)

This field asks for the company’s federal employer identification number.

Enter the nine-digit FEIN in the format 52-1234567. Use the number tied to the legal entity in Item 1, not a personal Social Security number unless you are a sole proprietor with no FEIN.

If your business is brand new and the FEIN is pending, note applied for with the application date so MDE can match records later. A common mistake is transposing digits, which can delay billing and tie your permit to the wrong taxpayer. Some filers believe the FEIN is optional for small shops, but MDE and the permit guide note that many permits require a Tax ID to check for state liabilities, so leaving it blank stalls processing.

Item 5: Equipment Description and Type

This field asks you to identify and describe the equipment you want to construct or modify.

Describe the equipment plainly, then give the make, model, and serial or model number. For example, Open-face paint spray booth, DeVilbiss Model PB-14, with dry filter media. Match the words on any purchase order or manufacturer spec sheet.

If you are modifying existing equipment rather than installing new, state the original permit number and describe the exact change. The most common mistake is a vague description like “new machine,” which forces MDE to send a deficiency notice for details. Filers often assume MDE knows the equipment from the brand name, but reviewers need capacity and design data to model emissions, so detail protects your timeline.

Item 6: Rated Capacity / Throughput

This field asks for the equipment’s design rate, such as units per hour, gallons per day, or heat input.

Enter the maximum rated capacity with units, drawn from the manufacturer data. For example, a printer writes press rated at 1,200 lbs of ink and solvent per day. Use the rated maximum, not your expected average, because emissions are judged at full capacity.

If the equipment runs in batches, give both the batch size and the number of batches per day or year. A common mistake is listing typical use instead of the rated maximum, which understates emissions and can make your permit unenforceable or trigger a reopening. People think reporting a lower number keeps fees down, but understating capacity is treated as an inaccurate application and can lead to denial.

Item 7: Process and Operating Schedule

This field asks how the equipment operates and how many hours it runs.

State the hours per day, days per week, and weeks per year, then describe the process steps. For example, 8 hours per day, 5 days per week, 50 weeks per year; parts are sprayed, then flash-dried at ambient temperature. This schedule converts hourly emissions into annual totals.

If you plan seasonal or round-the-clock operation, say so plainly, since 24/7 operation changes your potential-to-emit. The most common mistake is leaving the schedule blank or guessing low, which makes your annual emission estimate wrong and invites a deficiency notice. Filers often think operating hours are minor detail, but they directly set whether you stay a minor source or cross into more demanding permitting.

Item 8: Materials and Usage Rates

This field asks for the raw materials, coatings, fuels, or chemicals used and how much.

List each material with its maximum usage rate and attach the Safety Data Sheets. For example, Acme Hi-Solids Topcoat, 6.2 lbs VOC per gallon, 40 gallons per week. The VOC and toxic content from the SDS feed your emission math.

If you switch products often, list the worst-case material with the highest emission content. A common mistake is leaving out the SDS, which the MDE guide names as a top cause of delay because the air toxics demonstration cannot be verified. People assume “low-VOC” products need no documentation, but MDE still wants the data sheet to confirm the claim.

Item 9: Emission Estimates and Calculation Method

This field asks for the estimated emissions of each pollutant and how you calculated them.

Report emissions in pounds per hour and tons per year for each pollutant, and state your method. For example, VOC: 3.1 lb/hr, 4.0 tons/yr, calculated by mass balance from coating usage. Acceptable methods include EPA AP-42 emission factors, mass balance, or stack test results.

If you control emissions with a device, show both uncontrolled and controlled numbers and reference the Form 6. The most common mistake is giving a number with no calculation shown, which forces a deficiency notice and restarts the wait. Filers often think MDE will accept a round estimate, but reviewers must reproduce your math, so always attach the worksheet.

Item 10: Stack and Emission Point Data

This field asks for the physical details of each point where emissions leave the building.

Give stack height, inside diameter, exit gas temperature, and flow rate or velocity for each point. For example, Stack S-1: 30 ft tall, 18-inch diameter, exhaust at 95 degrees F, 4,000 cubic feet per minute. These numbers drive any ambient impact or dispersion analysis.

If two machines share one stack, identify that on the process flow diagram and complete one emission point entry. A common mistake is leaving stack height blank for a roof vent, which blocks the toxics ambient impact review under COMAR 26.11.15.06. People often think a small vent needs no data, but every discharge point that releases regulated pollutants must be described.

Item 11: Air Pollution Control Equipment

This field asks whether you use any device to reduce pollutants and to identify it.

If you have a control device, name it, give its design efficiency, and complete a Form 6. For example, Dry-filter booth, 98 percent particulate capture, see attached Form 6. If you have no control device, write None.

If you add a control device to existing equipment, you may need to file Form 6 on its own, as the MDE forms page explains. A common mistake is claiming a control efficiency with no supporting Form 6, which makes the claim unenforceable and can lower your allowed throughput. Filers often think the booth filters count automatically, but MDE only credits control it can document, so the Form 6 protects your numbers.

Item 12: Toxic Air Pollutant Demonstration (Forms 5T and 5EP)

This field asks whether your source emits toxic air pollutants and routes you to the supplements.

If your materials emit any toxic air pollutant under COMAR 26.11.15, attach Form 5T to summarize the T-BACT and ambient impact demonstration and Form 5EP for each stack’s estimated toxic emissions. For example, a printer using a chlorinated solvent completes one Form 5EP per emission point. Pull the toxic compounds straight from your SDS list.

If two pieces of equipment vent through one stack, file one Form 5EP and note both on the flow diagram, per the MDE instructions. The most common mistake is skipping these supplements, the exact gap MDE names as its leading cause of delay. Many filers assume small toxic amounts are exempt, but the demonstration is still required to prove you stay under the screening levels.

Item 13: Certification and Signature

This field asks an authorized official to sign and date the application, swearing the information is true.

Sign with a wet or electronic signature, print the name and title, and add the date in MM/DD/YYYY format. For example, Maria Lopez, Plant Manager, signed 06/04/2026. The signer must have authority to bind the company.

If you mail paper copies, the MDE forms page says each of the four copies must be signed and dated individually, not photocopied after signing. A common mistake is an unsigned or undated form, which makes the application invalid and resets your place in line. Filers often think a consultant can sign, but MDE wants a responsible company official, so confirm who has authority before submitting.

Three Filled-Out Examples Using Real Scenarios

Below are three common projects, each followed through Form 5 from top to bottom. Use them as models for your own entries.

Scenario 1: Carlos installs a paint spray booth at an auto body shop. Carlos owns a small collision shop and is adding one open-face spray booth with dry filters.

Form Section What Carlos Enters
Item 1: Company Name BAYSIDE AUTO BODY LLC
Item 2: Premises Address 1420 Pulaski Highway, Baltimore, Baltimore County, MD 21231
Item 4: FEIN 52-1234567
Item 5: Equipment Open-face paint spray booth, DeVilbiss PB-14, dry filter
Item 6: Rated Capacity Up to 12 gallons of coating per day
Item 8: Materials Hi-solids topcoat, 5.5 lb VOC/gal, plus SDS attached
Item 9: Emissions VOC 2.4 lb/hr, 3.1 tons/yr, mass balance
Item 11: Control Dry filter booth, 98% particulate, Form 6 attached
Item 13: Signature Carlos Reyes, Owner, 06/04/2026

Scenario 2: Janet adds a printing press at a commercial print shop. Janet runs a print business and is installing a heatset web press that uses solvent-based inks.

Form Section What Janet Enters
Item 1: Company Name CHESAPEAKE PRINT WORKS INC
Item 2: Premises Address 55 Industry Lane, Frederick, Frederick County, MD 21701
Item 5: Equipment Heatset web offset press, Heidelberg M-600
Item 6: Rated Capacity 1,200 lbs ink and solvent per day
Item 8: Materials Solvent-based ink, 30% VOC; cleanup solvent, SDS attached
Item 9: Emissions VOC 8.0 lb/hr, 9.5 tons/yr, AP-42 factors
Item 10: Stack Data Stack S-1, 35 ft, 20-inch dia, 250 F, 6,000 cfm
Item 12: Toxic Demo Forms 5T and 5EP attached for chlorinated solvent
Item 13: Signature Janet Cole, President, 06/04/2026

Scenario 3: Marcus installs a new natural-gas boiler (Form 11 path). Marcus manages a manufacturing plant adding a fuel-burning boiler, which uses Form 11, with Form 5 concepts shown for comparison.

Form Section What Marcus Enters
Company Name TIDEWATER MANUFACTURING CO
Premises Address 900 Harbor Road, Salisbury, Wicomico County, MD 21801
Equipment Natural-gas firetube boiler, Cleaver-Brooks CB-200
Rated Capacity 8.4 million Btu per hour heat input
Fuel Type Pipeline natural gas, 720 hours per year
Emissions NOx 0.84 lb/hr, 0.3 tons/yr, AP-42 factors
Stack Data Stack B-1, 40 ft, 16-inch dia, 350 F
Control Device Low-NOx burner, no separate Form 6
Signature Marcus Bell, EHS Manager, 06/04/2026

Note that Marcus uses Form 11 because boilers are fuel-burning equipment, and Forms 5T and 5EP are not required for that path. Aisha, a fourth filer running a quarry, would instead use Form 5 with a Form 6 for her dust collector.

How to File the Completed Form

You can file online, by mail, or with help from MDE staff. Pick one channel and keep proof of what you sent.

Online through the Environmental Service Center. This is now the fastest route. Go to the Environmental Service Center, upload your Form 5 and all supplements, and pay the fee by electronic payment. The portal lets you track status, and your confirmation screen and receipt are your proof of filing. Save a PDF of both.

By mail (paper copies). As the MDE forms page instructs, complete one application checklist, then make three photocopies of the completed form for a total of four. Sign and date each copy individually, send three to the Maryland Department of the Environment, Air and Radiation Administration, and keep one for your records. MDE invoices the fee after it reviews the package, so do not send payment until you receive the invoice; mail your check by certified mail and keep the receipt.

By phone or email for help. Call the Air Quality Permits Program at (410) 537-3225 or (410) 537-3230, or email MDE.Submit-AirPermits@maryland.gov. Larger projects should request a pre-submittal meeting, which the MDE guide recommends to speed review.

Fees range from about $400 to $20,500 depending on the source, as set in COMAR 26.11.02.17 and .18, and MDE tells you the exact amount after reviewing your application. Expect roughly 3 months for a routine permit and longer if public review applies.

What Happens After You File

First, MDE reviews your application for completeness and sends a deficiency notice if anything is missing. Once the file is complete, the agency invoices your fee, then examines the application for compliance with every air pollution control regulation, according to the MDE guide. Pay the invoice fast, because unpaid fees are a top cause of delay.

If your project is subject to public review under COMAR 26.11.02.11 and .13, MDE publishes a notice in the local paper, may hold an informational meeting, and prepares a draft permit available at the local library. The public can request a hearing, and any final determination is then subject to judicial review by participants. The agency strongly encourages you to engage neighbors early through community meetings, an Environmental Justice best practice that can reduce friction.

Once issued, the permit is a one-time approval. The MDE guide and Maryland OneStop both note that if construction does not begin within 18 months of issuance, the approval terminates. You may also need a new permit if you later change the equipment, process, material, or emissions.

Mistakes to Avoid When Filling Out the Form

Each error below has a direct consequence. Avoid them to protect your timeline.

  • Picking the wrong form. Using Form 5 for a boiler instead of Form 11 means MDE rejects the filing and you start over.
  • Skipping Forms 5T and 5EP. Missing the toxics demonstration is MDE’s top delay cause and freezes your application.
  • Leaving boxes blank. A blank field triggers a deficiency notice instead of being read as N/A.
  • Using a trade name instead of the legal entity. This can void or force a transfer of the permit.
  • Entering a P.O. Box as the premises address. This breaks the zoning and regional review and stalls processing.
  • Reporting typical use instead of rated capacity. Understating capacity can make the permit unenforceable or trigger a reopening.
  • Omitting Safety Data Sheets. Without SDS data, MDE cannot verify your air toxics numbers.
  • Showing emission numbers with no calculation. Reviewers must reproduce your math, so unsupported figures get bounced.
  • Forgetting stack parameters. Missing height or flow blocks the ambient impact analysis.
  • Claiming control efficiency without a Form 6. The claim becomes unenforceable and may cut your allowed throughput.
  • Submitting an unsigned or undated form. An unsigned application is invalid and loses its place in line.
  • Sending fewer than four paper copies. Mailing the wrong number delays intake under MDE’s filing rule.

Do’s and Don’ts

Do:

  • Do download the current form from MDE so your box numbers match, because outdated versions confuse reviewers.
  • Do attach every SDS and calculation worksheet, since MDE must verify your emission math.
  • Do call (410) 537-3225 before filing if you are unsure which form applies, to avoid a wrong-form rejection.
  • Do request a pre-submittal meeting for large projects, because it speeds the technical review.
  • Do keep a stamped or electronic proof of filing, so you can show the date you applied.
  • Do engage neighbors early when public review is likely, to reduce delay and opposition.

Don’t:

  • Don’t start construction before the permit issues, because building early is a violation that risks fines and shutdown.
  • Don’t pay the fee before MDE invoices you, since the agency sets the exact amount after review.
  • Don’t guess your operating hours low, because a wrong schedule distorts your annual emissions.
  • Don’t use a personal address for the premises, as it breaks the zoning and regional analysis.
  • Don’t skip the toxics supplements if any material emits a toxic air pollutant, or your file freezes.
  • Don’t photocopy after signing, because each paper copy must carry an original signature.

Pros and Cons of Filing on Your Own vs. With Help

Many filers can complete Form 5 alone, but complex sources often benefit from a consultant. Weigh both paths.

Pros of filing on your own:

  • Lower cost, because you avoid consultant fees on a simple project.
  • Direct control, since you know your equipment and process best.
  • Faster start for small sources, as a simple spray booth needs little modeling.
  • Better learning, because you understand your own compliance going forward.
  • Direct MDE contact, since the Permits Program offers free phone guidance.

Cons of filing on your own:

  • Higher rejection risk, because the toxics demonstration is technical and easy to miss.
  • Time cost, since gathering stack data and emission math takes effort.
  • Modeling gaps, as ambient impact analysis often needs specialized software.
  • Missed exemptions, because pros know the de minimis thresholds in COMAR 26.11.02.10.
  • Slower fixes, since deficiency notices can loop several times without expert help.

FAQs

Do I need a permit to construct before I install new equipment?

Yes. Any equipment that discharges emissions to the outside air needs an Air Quality Permit to Construct before installation, and building first is a violation that risks fines and a forced shutdown.

Do I use Form 5 for a boiler?

No. Boilers are fuel-burning equipment and use Form 11, while Form 5 covers general process equipment, spray booths, and printing presses.

Do I write my company’s legal name or trade name in Item 1?

Yes, use the legal entity name, because MDE cross-checks it against tax and zoning records and a trade name can void or delay the permit.

Do I put my mailing address in the premises address box (Item 2)?

No. Item 2 needs the physical site address, since a P.O. Box or billing address breaks the zoning and air quality region review.

Do I have to attach Safety Data Sheets?

Yes. SDS data lets MDE verify toxic and VOC content, and missing sheets are a top cause of application delay.

Do I need Forms 5T and 5EP for every application?

No, only when your source emits toxic air pollutants under COMAR 26.11.15, though incinerators on Form 10 always require them.

Do I report rated capacity or my expected use in Item 6?

Yes, report the maximum rated capacity, because emissions are judged at full design rate and understating it can make the permit unenforceable.

Do I pay the fee when I submit the application?

No. MDE invoices the exact fee after reviewing your application, and paying early or wrong can confuse billing.

Do I have to file by mail?

No. You can file online through MDE’s Environmental Service Center, pay electronically, and track status, or mail four signed copies instead.

Do I need to show how I calculated my emissions?

Yes. State your method, such as AP-42 factors or mass balance, because reviewers must reproduce your numbers or they send a deficiency notice.

Do I lose my permit if I delay construction?

Yes. If construction does not begin within 18 months of issuance, the approval terminates and you must reapply.

Do I have to demonstrate local zoning compliance?

Yes, for permits subject to public review, Section 2-404 requires proof of zoning compliance before MDE will process the application.

Do small toxic emissions get an automatic exemption on Form 5EP?

No. You still complete the demonstration to prove you stay under screening levels, even when the toxic amounts are small.

Do I need a separate Form 6 for my spray booth filters?

Yes, if you claim control efficiency credit, because MDE only counts control it can document through a Form 6.