How to Fill Out the Maryland MDE Wetlands and Waterways Permit (Joint Federal/State Application) + FAQs

The Maryland MDE Wetlands and Waterways permit is the Joint Federal/State Application you file when you plan to build, dig, fill, grade, or place a structure in or near any floodplain, waterway, tidal wetland, or nontidal wetland in Maryland. You send it to the Maryland Department of the Environment (MDE) Wetlands and Waterways Program, and it doubles as your request to the U.S. Army Corps of Engineers, so one form covers both the state and federal sides of your project.

If you skip this form and start work anyway, you risk a stop-work order, fines, and an order to rip out what you built and restore the site. MDE reviews thousands of these applications each year, and many get delayed because of a single missing piece, such as a wetland delineation report or a poor-quality site plan. This guide walks you through the current April 2018 version of the form, line by line, so your application moves forward the first time.

Here is what you will learn:

  • πŸ—ΊοΈ How to read each block of the form and enter the right answer in plain language
  • πŸ’΅ What fee to send based on your project type, using the current 2025 Fee Schedule
  • πŸ“ Which maps, plans, and delineation reports you must attach so the review starts on day one
  • 🏠 Three full walkthroughs for a pier, a pond, and a small wetland fill, with real numbers
  • ⚠️ The field-level mistakes that trigger denials and how to dodge each one

What the Form Is and Who Must File It

The Joint Federal/State Application is the single document MDE and the Army Corps of Engineers use to review any change to Maryland’s regulated waters. The full title is the Joint Federal/State Application for the Alteration of Any Floodplain, Waterway, Tidal or Nontidal Wetland in Maryland. The form carries a revision date of 4/2018 in the bottom corner, so check that you have that version before you start. MDE’s Wetlands and Waterways Program receives the state side, and the Corps Baltimore District receives the federal side.

You must file this form if your project disturbs a tidal wetland, a nontidal wetland, the 25-foot or 100-foot nontidal wetland buffer, a stream, a pond, a river, or the 100-year floodplain. The state’s authority comes from Title 5 of the Environment Article (Subtitles 5 and 9) and the rules in COMAR Title 26. The federal side rests on Section 404 of the Clean Water Act and Section 10 of the Rivers and Harbors Act, which the Corps enforces.

The plain-English version is this: if you move dirt, water, or plants in or beside a wetland or waterway, you almost certainly need this form. Common filers include homeowners building a pier or shoreline, contractors crossing a stream with a driveway, and developers grading a lot near a wetland. Even some “exempt” activities still require the form so MDE can confirm the exemption applies. When you ignore this rule, MDE can issue a penalty and force restoration, so file first and build second.

A frequent misconception is that small backyard jobs are too minor to regulate. In truth, a project as small as a deck footing in a nontidal wetland triggers the form, because the law measures impact by location, not by size alone.

Before You Start: Documents and Information You Need

Gather everything below before you open the form, because MDE gives you only one chance to fill gaps after the 45-day completeness letter. Missing items are the top reason applications stall. Use this pre-filing checklist:

  • Owner’s full legal name, address, phone, and email. The landowner must sign, so the name here must match the deed, or MDE returns the form as incomplete.
  • Agent, engineer, or consultant contact details. If a pro acts for you, MDE needs their info to send questions, and a missing agent line slows every later step.
  • A wetland delineation report and data sheets. The Corps Wetlands Delineation Manual (Technical Report Y-87-1) sets the method, and without this report MDE cannot confirm your impact area.
  • A vicinity map with the site pinpointed. Seven copies are required, and a map that does not show the property boundary gets rejected on intake.
  • Site plans with plan view and section view. These must show contours, dimensions, wetlands, buffers, and the limit of disturbance, or the review cannot begin.
  • Square footage of every impact. You report wetland, buffer, stream, and floodplain impacts in square feet, and a guess here can push you into a higher fee tier or a denial.
  • Latitude and longitude of a central project point. MDE uses this to locate your site on its maps, and a wrong coordinate can route your file to the wrong reviewer.
  • Names and addresses of adjacent property owners. Block 9 requires them, and skipping this step can delay any project that needs a public notice.
  • The correct application fee. The standard fee is $750, but project-specific fees in the 2025 Fee Schedule may apply, and the wrong amount stalls intake.
  • Any other approvals you have sought. Block 10 asks for county grading permits, Critical Area approvals, and the like, and leaving it blank looks like an incomplete record.

Take time to confirm each item is on hand. MDE advises that you delay filing until everything is ready, because a complete package is the fastest path to a permit.

Where to Get the Form and How to Access It

You can download the current form from two official sources. The MDE Application Forms page hosts the Joint Federal/State Application and its instructions. The Corps Baltimore District also posts the same Maryland Long Form on its regulatory page. Both lead to the identical 4/2018 version, so either source works.

You have a choice of paper or online filing. For paper, you print the PDF, fill it out, and mail one original plus six copies. For online filing, MDE accepts tidal, nontidal wetland, and nontidal waterway applications through its Environmental Service Center, and the state’s OneStop portal also routes these permits.

Before you file either way, MDE strongly suggests a pre-application meeting for anything complex. You request one by submitting the Pre-Application Meeting Request Form, or by calling the program at 410-537-3745 or 1-800-633-6101. A short call up front often saves months later, because the reviewer tells you exactly what plans and studies your project needs.

A common misconception is that the online portal is a different, easier permit. It is the same application and the same review standards; only the delivery method changes. Choose the channel that fits your comfort with uploading large plan files.

Step-by-Step: How to Fill Out the Joint Federal/State Application Line by Line

Work through the form in the order it prints. Each block below tells you what it asks, how to answer, an example, an edge case, the mistake to avoid, and a myth to drop.

Top of Form: Submission Type and Date

The top of page one asks you to check one box: Resubmittal, Application Amendment, Modification to an Existing Permit, Jurisdictional Determination Only, or Applying for Authorization. You also enter the date and any previously assigned number for resubmittals and amendments.

To answer, check Applying for Authorization if this is your first request for a new project. Write the date in MM/DD/YYYY format, such as 06/04/2026. Leave the previously assigned number blank unless you are resubmitting.

For example, James Carter starts a brand-new pier project, so he checks Applying for Authorization and leaves the prior-number line empty.

An edge case: if MDE denied an earlier version of your project for insufficient information, you check Resubmittal and enter the old number, and a new fee is due because a resubmittal counts as a new application.

A common mistake is checking Modification when you actually have a fresh project, which routes your file to the wrong queue and adds weeks. The myth to drop is that Jurisdictional Determination Only is a shortcut to permission; it only confirms whether waters are regulated, not whether you may build.

Block 1: Applicant Information

Block 1 collects contact details for up to five roles: Applicant, Agent/Engineer, Environmental Consultant, Contractor, and Principal Contact. Each role has fields A through F for name, daytime telephone, company, email, address, and city/state/zip.

Fill in the Applicant block with the landowner’s details exactly as they appear on the deed. Complete the Agent/Engineer and Consultant blocks only if those people work on your project. Always name a Principal Contact so MDE knows who to call.

For example, James Carter enters his name, 410-555-0148, his email, and his Annapolis home address in the Applicant block, then lists his marine contractor under Contractor.

An edge case: if you hire a consultant to act for you, list them as Agent and they can answer MDE’s questions, but the landowner still must sign the certification at the end.

The common mistake is leaving the Principal Contact blank, which means MDE may call the wrong person and lose days waiting for a reply. The myth here is that the contractor can sign for the owner; only the landowner’s signature makes the form complete.

Block 2: Project Description

Block 2a asks for a written description of the project, whether any part is already done, whether it is a residential subdivision or commercial development, and whether tree clearing will occur with the total acres cleared. Block 2b asks you to check the activities proposed, such as filling, dredging, excavating, draining, grading, removing or destroying vegetation, or building structures, and to list the impact areas in square feet. Block 2c is a dimensions table for each structure type, and Block 2d asks for the project purpose.

Describe the work in clear, simple terms, then check every activity that applies. Enter wetland, buffer, and stream impacts in square feet, and fill the dimensions table with length, width, and area for each structure.

For example, James writes Construct a 60-foot private pier with a 200-square-foot platform for personal boat access, checks building structures, and enters Pier: length 60, width 4 in row H of the table.

An edge case: the 4/2018 form added a tree-clearing question, so if you will clear any trees on the whole site, check Yes and enter the acres, such as 0.10 acres, even when the clearing is in uplands.

A common mistake is underreporting square footage to dodge a higher fee, which backfires when MDE measures your plans and recalculates, delaying the review. The misconception is that “project description” means a one-word answer; reviewers need enough detail to picture the finished work.

Block 3: Project Location

Block 3a asks for the county, city, nearest waterway, state stream use class, site address, directions from two state roads, whether you are in the Chesapeake Bay Critical Area, map coordinates, FEMA panel number, and latitude and longitude. Block 3b asks you to check the type of water you will affect, and Block 3c asks for current land use, zoning, and whether the project complies with zoning.

Enter the location data from your survey and a mapping tool. Check the Critical Area box Yes if your site sits within about 1,000 feet of tidal water. Mark the activity location, such as Tidal Waters or Nontidal Wetland, and confirm zoning compliance.

For example, James enters Anne Arundel county, names the Severn River, checks Yes for the Critical Area, and records latitude 39.0287 and longitude -76.5197.

An edge case: if your project crosses a county line or sits in Garrett or Somerset County, the Alexandria Drafting Co. map coordinates do not apply, so you rely on latitude and longitude instead.

The common mistake is guessing the Critical Area answer, which matters because Critical Area projects face extra review and stricter limits. The myth is that the stream use class is optional; MDE uses it to judge water quality protection, and a blank slows the file.

Blocks 4 Through 7: State Review Questions

Blocks 4 through 7 are required by the state. Block 4 asks how you avoided or reduced wetland impacts and why some impacts remain. Block 5 is the Letter of Exemption block for small nontidal work. Block 6 is the alternative site analysis, and Block 7 asks about the public need or benefit.

Answer Block 4 by checking the steps you took, such as Reduced the area of disturbance, and writing a short explanation. Skip Blocks 6, 7, 8, and 9 if you check the exemption box in Block 5; otherwise complete them.

For example, a developer named Priya Nair checks Redesigned project in Block 4 and explains that she shifted a driveway 15 feet to shrink the wetland fill.

An edge case: if you apply for a letter of exemption in Block 5, the form tells you to proceed straight to Block 10 and leave the alternatives, public need, mitigation, and notification blocks empty.

The common mistake is leaving Block 4’s explanation blank, since the law requires you to show you avoided and minimized harm first, and an empty box reads as no effort. The misconception is that “public need” only means government projects; a private pier can still describe safe water access as its benefit.

Block 8: Mitigation Plan

Block 8 asks for your mitigation plan when your project causes wetland or waterway loss. It has four parts: any monetary compensation proposal, a description of the mitigation project, why you chose the mitigation site, and how the site will be protected long term.

Complete this block only if you are not claiming an exemption and your project causes loss. Describe how you will replace the lost wetland, often at a ratio set by MDE, and how a conservation easement or similar tool will protect it.

For example, Priya proposes to create 0.15 acres of new wetland on the same parcel and protect it with a recorded easement.

An edge case: if on-site mitigation is not possible, you may propose payment into the state in-lieu fee program, and you note that as your monetary compensation proposal.

The common mistake is treating mitigation as an afterthought, which can stall a permit because MDE will not approve a loss without a credible replacement plan. The myth is that mitigation is always optional; for permanent wetland loss it is usually a condition of approval.

Blocks 9 Through 12: Notice, Approvals, History, and Extras

Block 9 asks whether you notified adjacent property owners and lists their names and addresses. Block 10 lists other approvals needed or granted. Block 11 asks if the project is near historic properties. Block 12 is open space for added detail, plus a checklist of enclosed data like soil borings, wetland data sheets, photographs, and site plans.

Check Yes in Block 9 and list every neighbor that shares a boundary. In Block 10, list county and Critical Area approvals. Answer Block 11 honestly, and use Block 12 to attach anything that did not fit earlier.

For example, James lists his two waterfront neighbors with their mailing addresses in Block 9 and checks Site plan and Photographs in the data checklist.

An edge case: if you do not know whether a historic property is nearby, you may check Unknown in Block 11, and the Corps will research it during review.

The common mistake is skipping adjacent-owner notice, which can derail any project that needs a public notice and invites neighbor objections later. The misconception is that Block 10 is only for permits already granted; you also list approvals you have merely applied for.

Certification and Landowner Signature

The certification block is where the landowner signs and dates the form. By signing, you swear the information is true, that all wetlands were delineated by the Corps manual, and that you grant inspectors site access and will not start work without authorization.

Read the certification, then have the legal landowner sign and date it. The signature must be the owner’s, even if an agent prepared everything else.

For example, James Carter signs his own name and writes 06/04/2026 as the date.

An edge case: if the property has co-owners, MDE may need each owner’s signature, so confirm with the program when title is shared.

The common mistake is mailing the form unsigned, which the instructions warn will deem the application incomplete and stop the clock. The myth is that an electronic or agent signature always suffices; for paper filings, the program expects the landowner’s signature on the certification line.

Three Filled-Out Examples Using Real Scenarios

Below are three common filers walked through the major blocks of the form.

Scenario 1: James Builds a Private Pier (Tidal)

James Carter wants a 60-foot pier with a 200-square-foot platform on the Severn River in Anne Arundel County.

Form Section What James Enters
Submission type Checks Applying for Authorization, dates it 06/04/2026
Block 1 Applicant James Carter, Annapolis address, phone, email
Block 1 Contractor His licensed marine contractor’s name and phone
Block 2a Description Construct a 60-foot private pier with a 200 sq ft platform
Block 2b Activity Checks building structures, notes platform area 200 sq ft
Block 2c Dimensions Row H Pier: length 60, width 4, channelward 60
Block 3 Location Anne Arundel, Severn River, Critical Area Yes
Block 3 Coordinates Latitude 39.0287, longitude -76.5197
Block 9 Neighbors Lists two adjacent waterfront owners
Certification Signs as landowner, dates 06/04/2026

James includes seven copies of a plan view showing the mean high water line and a section view of the pier.

Scenario 2: Maria Builds a Small Pond and Stream Crossing (Nontidal)

Maria Lopez plans a small farm pond and a driveway culvert across a nontidal stream in Frederick County.

Form Section What Maria Enters
Submission type Checks Applying for Authorization
Block 2a Description Build a 0.2-acre pond and a 24-inch culvert driveway crossing
Block 2a Tree clearing Checks Yes, enters 0.15 acres
Block 2b Activity Checks excavating, filling, grading
Block 2b Impact area Stream impact 180 sq ft, length affected 30 linear feet
Block 2c Dimensions Row N Small Pond and Row R Culvert with sizes
Block 3b Location type Checks Nontidal Wetland and In stream channel, Nontidal
Block 4 Reduction Checks Reduced size/scope of project
Block 8 Mitigation Describes replacing lost stream function on site
Certification Signs as landowner

Maria attaches a wetland delineation report and a large-scale impacts map at 1 inch = 200 feet.

Scenario 3: Priya Fills a Small Nontidal Wetland for a Driveway

Priya Nair, a small developer, needs to fill under 1,000 square feet of nontidal wetland for a non-habitable driveway in Howard County.

Form Section What Priya Enters
Submission type Checks Applying for Authorization
Block 2a Description Place driveway fill, 950 sq ft permanent nontidal wetland impact
Block 2b Activity Checks filling and grading
Block 2b Impact area Wetland 950 sq ft
Block 3b Location type Checks Nontidal Wetland
Block 4 Reduction Checks Redesigned project, shifted driveway 15 feet
Block 5 Exemption Checks not applying for exemption
Block 8 Mitigation Proposes 0.15 acres on-site wetland creation
Block 9 Neighbors Lists two adjacent owners
Certification Signs as landowner

Priya sends the non-habitable structure fee of $390 because her permanent impact stays at or below 1,000 square feet.

How to File the Completed Form

You can file by mail or online, and the channel sets where your documents and fee go. Keep proof of filing no matter which path you pick.

By mail. Send one original plus six copies of the application, plans, maps, and reports to the Maryland Department of the Environment, Water and Science Administration, Regulatory Services Coordination Office, 1800 Washington Boulevard, Suite 430, Baltimore, Maryland 21230. The office line is (410) 537-3762 or 1-800-633-6101. Mail the application fee and a copy of the first page separately to MDE, P.O. Box 2057, Baltimore, MD 21203-2057, with PCA 13910 and OBJ 4142 noted. Pay by check or money order to the Maryland Department of the Environment, and keep a certified-mail receipt as your proof.

Online. Submit through MDE’s Environmental Service Center or the state’s OneStop portal, where you upload the form and plans and pay the fee by card or e-check. Save the confirmation number the portal gives you, since that is your proof of filing.

The standard application fee printed on the form is $750, but the 2025 Fee Schedule sets activity-specific fees that often apply, such as $390 for small non-habitable nontidal structures, $980 for many minor projects, and $1,950 for major projects under a quarter acre. Some projects, such as living shorelines and vegetative shoreline stabilization, carry no fee but still need the application. A separate Tier II review fee may be invoiced later if your site sits in a Tier II watershed.

Expect a review window measured in months. MDE sends a 45-day letter telling you the work is authorized or that more information is needed, and minor projects often take several months while public-notice projects take longer.

What Happens After You File

After MDE logs your application, a reviewer checks it for completeness and may perform a field review at your site. Within about 45 days, MDE mails the 45-day letter that either authorizes the activity or lists the additional information it needs. This letter is the heart of the process, so read it closely and note its deadline.

The 45-day procedure, in place since August 1, 2011, gives you only one chance to supply missing information. If you miss the deadline or your response is still short, MDE denies the application for insufficient information, and you must reapply and pay a new fee. Stay in contact with your assigned project manager so you answer the letter fully and on time.

For larger or public-notice projects, MDE and the Corps may publish notice and accept public comment before deciding. Once approved, your authorization comes with conditions, such as work windows and stabilization steps, and you must follow them. A common misconception is that approval lets you build anything similar later; any change usually needs a modification application.

Mistakes to Avoid When Filling Out the Form

  • Mailing the form unsigned: the application is deemed incomplete and the review never starts.
  • Sending fewer than seven total copies: MDE will not begin review until all copies arrive.
  • Leaving out the wetland delineation report: the reviewer cannot confirm your impact area and stalls the file.
  • Underreporting impact square footage: MDE remeasures from your plans and the mismatch delays or denies the permit.
  • Guessing the Critical Area answer: a wrong answer skips required extra review and can void an approval.
  • Skipping the tree-clearing question added in 2018: the Corps treats the form as incomplete.
  • Forgetting adjacent property owner names in Block 9: public-notice projects cannot proceed without them.
  • Submitting cluttered or unscaled plans: poor-quality drawings are grounds for an incompleteness finding.
  • Sending the wrong fee amount: intake pauses until the correct fee posts.
  • Naming the contractor as the signer: only the landowner’s signature makes the form valid.
  • Ignoring the 45-day letter deadline: MDE denies the application and you start over with a new fee.
  • Leaving the project purpose vague: reviewers cannot judge avoidance and minimization without it.

Do’s and Don’ts

Do:

  • Request a pre-application meeting for anything complex, because the reviewer tells you what to attach.
  • Match the applicant name to the deed, since a mismatch blocks the signature.
  • Report every impact in square feet, because fees and review depend on accurate numbers.
  • Include seven copies of all documents and the vicinity map, since that starts the clock.
  • Keep your certified-mail receipt or portal confirmation as proof of filing.
  • Answer the 45-day letter fully and early, because you get only one chance.

Don’t:

  • Don’t start any work before you receive authorization, or you risk fines and restoration.
  • Don’t shrink your numbers to chase a lower fee, since MDE remeasures from plans.
  • Don’t leave state Blocks 4 through 7 blank when you are not exempt.
  • Don’t forget the landowner’s signature on the certification.
  • Don’t submit blurry or unscaled plan sheets.
  • Don’t assume a small backyard project is exempt without confirming it.

Pros and Cons of Filing on Your Own vs. With Help

Filing on Your Own Filing With a Consultant or Engineer
Saves consultant fees, good for simple projects like a no-fee living shoreline Costs more, but a pro prepares plans and delineations that pass intake
You learn your property and the rules firsthand Saves your time and reduces back-and-forth with MDE
Full control over timing and edits Faster fixes when MDE asks for more information
Risk of missing a required attachment and stalling Lower risk of an incompleteness finding
Harder to judge mitigation ratios alone Pro knows current mitigation and Tier II expectations
Works best for clearly minor, low-impact work Best for tidal, large, or public-notice projects

FAQs

Do I need this form for a small backyard project in a wetland?

Yes. Even a deck footing or driveway in a nontidal wetland needs the Joint Federal/State Application, because Maryland regulates by location, not only by project size.

Do I have to file with both the state and the Corps separately?

No. The single Joint Federal/State Application covers both, and MDE shares it with the Army Corps of Engineers Baltimore District for federal review.

Do I write the contractor’s name in the applicant block?

No. Block 1’s Applicant fields take the landowner’s legal name and details; the contractor goes in the separate Contractor block lower in Block 1.

Do I check “Applying for Authorization” or “Modification” for a brand-new project?

Yes, check Applying for Authorization for any new project; Modification is only for changing a permit MDE already issued.

Do I report impacts in acres or square feet in Block 2b?

No, not acres for the impact lines; Block 2b asks for wetland, buffer, and stream impacts in square feet, while tree clearing is reported in acres.

Do I answer the Critical Area question if I live far from the bay?

Yes. Check No if your site is not within about 1,000 feet of tidal water, but you must still answer the question in Block 3.

Do I need a wetland delineation report to file?

Yes. You must delineate wetlands using the Corps Wetlands Delineation Manual and attach the report and data sheets, or MDE cannot confirm your impacts.

Do I have to notify my neighbors before filing?

Yes for most projects; Block 9 asks for adjacent property owner names and addresses, and missing them stalls any project needing public notice.

Do I send the fee with the application or separately?

No, not in the same envelope for mail filings; send the fee plus a copy of the first page to MDE’s P.O. Box 2057 lockbox in Baltimore.

Do all projects pay the $750 fee on the form?

No. Many projects use activity-specific fees in the 2025 Fee Schedule, such as $390 for small non-habitable nontidal structures or no fee for living shorelines.

Do I lose my fee if MDE denies my application?

Yes, in effect, because a resubmittal counts as a new application and a new fee is due when you reapply.

Do I have to sign the form myself if I hired an agent?

Yes. The landowner must sign the certification block; an agent can prepare and submit, but only the owner’s signature makes the application complete.

Do I need seven copies even for online filing?

No. Online filing through the Environmental Service Center or OneStop replaces the seven paper copies; the seven-copy rule applies to mailed submissions.

Do I include uplands tree clearing in the 2018 tree-clearing question?

Yes. The added question asks for total tree clearing across the whole site, including uplands and wetlands, so report all acres cleared.