The MassDEP Air Plan Approval Application is the form a facility owner or operator files with the Massachusetts Department of Environmental Protection to get written permission before building, rebuilding, or changing any equipment that releases air pollution. You file it through the state’s online EEA ePLACE Portal, and you must hold an approval in hand before you pour a foundation, bolt down a boiler, or fire up a process line.
This permit protects public health and the air your neighbors breathe, which is why the agency reviews every line so closely. Getting a field wrong can stall your project for months, and starting construction without the written approval can bring penalties under 310 CMR 5.00. The current online forms carry a September 2019 revision date, so confirm you are working in the up-to-date ePLACE version before you start. A Major Comprehensive Plan Application (BWP AQ 03) carries a filing fee of $24,305, while a Non-Major (BWP AQ 02) costs $2,370, so the stakes are real from the first click.
In this guide, you will learn:
- 🏭 What the Plan Approval form is, which tier applies to you, and who must file it
- 📋 The exact documents and numbers to gather before you open the online form
- 🖥️ A step-by-step walkthrough of every screen in the ePLACE application
- 🧑💼 Three real filled-out scenarios you can copy from start to finish
- ⚠️ The field-level mistakes that get applications rejected and how to dodge them
What the Form Is and Who Must File It
The Air Plan Approval Application is MassDEP’s permit to construct. The agency issues an approval to limit increases in air contaminant emissions and to protect public health, welfare, and the environment. You need one if you propose construction, substantial reconstruction, or alteration of a facility that has the potential to cause or contribute to a condition of air pollution. The legal engine behind the form is 310 CMR 7.02, and the Legislature authorized those rules through M.G.L. Chapter 111, Sections 142A–J.
There is more than one version of this application, and picking the right one is your first real decision. The two main families are the Limited Plan Application (LPA) for smaller or simpler sources, and the Comprehensive Plan Application (CPA) for larger or more complex ones. Within the CPA group sit five forms: Major CPA Process, Major CPA Fuel Utilization, Non-Major CPA Process, Non-Major CPA Fuel Utilization, and Non-Major CPA Crematory.
The trigger for a CPA-Process is clear. Any non-combustion process unit that has the potential to emit 10 tons or more of any single air contaminant in any consecutive 12-month period needs a CPA-Process approval. Fuel-burning equipment follows size thresholds instead. A natural gas or propane boiler at 40 MMBtu/hr or more, or a distillate fuel oil boiler at 30 MMBtu/hr or more, needs a CPA-Fuel, as the CPA instructions spell out in their applicability tables.
Some sources skip the full form. The agency allows exemptions under 310 CMR 7.02(2), Permit-by-Rule categories under 310 CMR 7.03, and Environmental Results Program (ERP) compliance certifications under 310 CMR 7.26 in place of a written Plan Approval. Check those carveouts first, because filing a full CPA when a Permit-by-Rule would do wastes both money and months.
Before You Start: Documents and Information You Need
Open the form only after you have your full file in front of you. The ePLACE system saves your work, but missing data is the top reason applications stall at the administrative-completeness stage. Below is the pre-filing checklist. Each item matters, and each gap has a cost.
- An active EEA ePLACE account for every party. The preparer, the Professional Engineer, and the Permittee each need their own account, because the form is shared by login, not by a PIN. Without all three accounts, you cannot route the form for certification, and submission stalls.
- Your facility’s SIC or NAICS code. The form asks for a Standard Industrial Classification code or a NAICS code. A wrong code misroutes your application and can flag the wrong review path.
- Manufacturer specifications for every emission unit. These prove your equipment’s size, rating, and emission factors. Without them, MassDEP cannot verify your numbers and will ask for them anyway.
- Emission calculations for each contaminant. You need potential-to-emit figures in tons per year. These decide whether you are Major or Non-Major, which sets your fee.
- A list of existing air approvals at the site. The form asks for prior approvals so the agency can see your full emissions picture. Leaving one out can look like you are hiding emissions.
- Stack and pollution control device details. Heights, diameters, flow rates, and control efficiencies feed the agency’s review. Missing stack data blocks the air quality review entirely.
- A MEPA determination. Check the Massachusetts Environmental Policy Act thresholds, because MassDEP cannot finish technical review until any MEPA process is done.
- A draft EJ Project Fact Sheet (for CPA-Process). MassDEP directs CPA-Process filers to attach a two- to four-page Project Fact Sheet describing the project and neighboring communities. Skip it and your application is incomplete.
- Your filing fee payment method. Have a credit card, electronic check, or paper check ready, because the review clock does not start until the fee clears.
A smart move before any of this is a pre-application conference with your MassDEP Regional Office. The agency strongly suggests it, and if you skip it, MassDEP may require one before it will even call your application administratively complete.
Where to Get the Form and How to Access It
The Air Plan Approval Application lives online. You complete it through the EEA ePLACE Portal, which is the single front door for MassDEP air permits. There is no fillable master PDF you mail in by default; the online form is the standard channel, and the agency built it to route the form among the preparer, engineer, and owner.
Your first step on the portal is to create an account. Every person who will touch the application needs one, since the system grants access by login. Once the first preparer opens an application and lists the other parties, those people gain access to help build it. The screen-by-screen guide on Mass.gov walks through each page with images, and it also gives a field-by-field description of what content and format each box expects.
A key rule about the online form: every field marked with a red asterisk must be filled before you can move to the next page. But many fields are not marked required and still must be completed for the application to be administratively or technically complete. Do not assume a box is optional just because it lacks a red asterisk, because the agency reviews the whole record, not just the starred fields.
If you truly cannot file online, you may request a paper form from your regional office and mail it back to the attention of the BAW Regional Data Manager. This is the exception, not the rule, and paper filings often move slower because staff must key them in. For almost every filer, the portal is the faster and safer path.
Step-by-Step: How to Fill Out the MassDEP CPA Line by Line
The application moves through seven numbered steps inside ePLACE, and most of your time lives in the data tables of Step 3. Below, each step gets its own walkthrough. Follow them in order, because the form unlocks later sections based on answers you give earlier.
Step 1: Contact Information
This screen asks you to name everyone who will work on the application: the preparer or preparers, the applicant (called the Permittee), and the Massachusetts Registered Professional Engineer (PE). You also flag who the Submitter will be, meaning the one person allowed to edit the form after submittal if MassDEP asks for more.
To answer it, the first person to open the application enters each party by the ePLACE account tied to them. All parties must already hold an ePLACE account before you can list them here, so set those up first. Once you save the page, everyone you listed gains access to the shared form.
For example, Carlos Reyes, an environmental consultant, lists himself as Preparer, lists his client’s plant manager as the Permittee, and lists his firm’s licensed PE by her account email. He marks himself as Submitter so he can fix any agency comments fast.
A common edge case is a project where the consultant and the owner want the owner to keep control. In that case, name the Permittee as the Submitter instead, since the Submitter is the only one who can edit after filing. A frequent mistake here is listing a PE who lacks an ePLACE account, which freezes the whole certification chain and the form cannot be routed. The misconception to drop is that this is just a “contacts” page; it actually sets who can legally edit and certify your permit, so treat it as a control panel, not a formality.
Step 2: Facility and Owner Information
This section captures the facility name and address along with the facility owner. In plain terms, it asks where the equipment sits and who owns the site.
To answer it, search first from the pre-loaded list of known facilities. If your site is already in the system, selecting it pulls in the address and avoids typos. If the facility is new or not listed, enter the information by hand and do not pick from the existing list.
For example, Janet Okafor files for a new coating line at “Bay State Finishing, 14 Industrial Way, Fall River, MA 02720” and types it in fresh because the site has never held an air permit. For owner and contact data, if you filed online before for the same facility, you can look up and reuse the ownership record.
The edge case to watch is a recent change in ownership; pick the current legal owner, not the prior one, because the approval attaches to the equipment and the owner of record. A common mistake is creating a duplicate facility record when one already exists, which scatters your site’s permit history and confuses reviewers. The misconception to correct is that the mailing address equals the facility address; the physical location of the equipment is what drives the air quality review, so enter the real site, not a headquarters P.O. Box.
Step 3: Application Information
This is the heart of the form and the largest section. The first page links back to the instructions and asks several general questions, then later pages open a series of data tables.
To answer it, start by entering your SIC code or NAICS code, then state whether the project is subject to MEPA review. Click “Continue Application” to reach the table pages. On Page 2 you enter your List of Existing Approvals. On Page 3 you write a brief Description of Project, mention any proposed pollution control devices, and answer Regulatory Information questions, including whether the project alters previously approved equipment or is subject to Federal New Source Review under 310 CMR 7.00 Appendix A.
For example, Marcus Bell describes his project as “Installation of one 38 MMBtu/hr natural gas boiler with low-NOx burner and flue gas recirculation” and selects his SIC code for industrial laundries. On Page 4, if you flagged Appendix A on Page 3, you identify the emission reduction credits you will use. On Page 5, you state whether the project triggers federal Prevention of Significant Deterioration (PSD) review and describe how you reached that conclusion. On Page 6, a table asks you to list each applicable federal Part and Subpart, such as New Source Performance Standards or MACT, for each emission unit. Each application also includes an Energy Efficiency Survey on a page whose number varies.
The CPA-Process and CPA-Fuel forms then branch into their own tables. A Process form asks for Project Equipment details, any Ancillary Fuel use, Pollution Control Device (PCD) details, the supplemental forms each PCD needs, Project Configuration showing how the unit, control device, and stack connect, Proposed Stack details, Best Available Control Technology (BACT) emissions, and Monitoring and Recordkeeping. A Fuel form adds Fuel(s) details and Noise and Odor questions on top.
The edge case many filers miss is the PSD question; if you answer yes, you must attach extra PSD material that the online form does not collect, so call your regional office first. A common mistake is leaving the BACT table blank or claiming top-case BACT without a backup analysis, which forces a deficiency notice and a delay. The misconception to drop is that the “brief” project description can stay vague; reviewers use it to frame the whole permit, so name the equipment, its rating, and its controls plainly.
Step 4: Documents
This step asks you to attach supporting documents to the application. In plain English, it is where you upload the proof behind your numbers.
To answer it, click “Browse,” find the file on your computer, attach it, then pick the attachment type from the drop-down and write a short description. The process works just like attaching a file to an email. Upload manufacturer specifications, your BACT analysis if you are not proposing top-case BACT, emission calculations, and plot plans.
For CPA-Process filers, this is also where you attach the EJ Project Fact Sheet; select “Other” as the category and type “Fact Sheet” in the description, as the CPA-Process page directs. For example, Aisha Nguyen attaches a 12-page boiler cut sheet, a 3-page BACT memo, and a 3-page EJ Fact Sheet, labeling each one clearly.
The edge case is a file that exceeds the upload size limit; split a large modeling report into parts rather than skipping it. A common mistake is attaching documents with vague names like “scan1.pdf,” which slows the reviewer who cannot tell what they are opening. The misconception to correct is that you should attach only the minimum; the agency openly encourages more than the minimum, because a fuller record speeds review.
Step 5: Special Fees
This step covers special fee circumstances spelled out in 310 CMR 4.00. It is separate from your base filing fee.
To answer it, most applicants will not face special fees, but if you do, pick the applicable fee exemption type and provide the supporting information on this page. For example, a municipal applicant claiming a government exemption selects that exemption type and uploads proof of its public status.
The edge case is a nonprofit or government filer who qualifies for a reduced or waived fee but forgets to claim it here, then overpays. A common mistake is selecting an exemption you cannot support, which triggers a request for documentation and delays the fee verification. The misconception to drop is that this page sets your main permit fee; it does not, since your base CPA fee is fixed by your Major or Non-Major status and is paid later in Step 7.
Step 6: Application Review
This step shows the entire application for a final read-through before you commit. It is your last clean chance to catch errors.
To answer it, read every page, and if you spot a problem, click “Edit Application” at the top to reopen and fix it. When the record is complete and accurate, proceed toward submission. For example, Carlos Reyes scrolls the full review screen, notices the stack height was entered in feet where meters were expected, fixes it, and only then continues.
The edge case is a multi-party form where one preparer changed a value the others have not seen; review together before moving on. A common mistake is rushing past this screen, since errors caught here cost minutes while errors caught after submittal cost weeks. The misconception to correct is that you can freely edit anything later; after submittal, only the Submitter can edit, and only when MassDEP opens the record back up.
Step 7: Authorization Forms and Certification
This final step holds the Supplemental Forms, such as the technical sheet for a Selective Catalytic Reduction unit, plus the certification forms the Permittee and PE use to accept the filing. It is where the application becomes legally real.
To answer it, complete each supplemental form listed by clicking the link to its right; if a form you need is missing, return to Application Information and add it. The Submitter then certifies and clicks “Submit,” which creates a Permit Application number and emails the PE and Permittee to accept the submittal. The PE logs in next, reviews, and certifies with a separate statement that includes their license number and expiration date. The Permittee certifies last, and the application is not formally submitted until both accept.
For example, the PE, Dr. Elena Ruiz, reviews the boiler tables, enters her PE license number and expiration date, and certifies; the plant manager then accepts as Permittee. After the Permittee accepts, they return to “My Records” and click the permit fee link to pay online by card or electronic check, or by mailed check.
The edge case is a PE or Permittee who disagrees and denies acceptance, which returns the form to the Submitter for fixes rather than killing it. A common mistake is forgetting that the PE’s license must be current; an expired license number invalidates the certification. The misconception to drop is that hitting “Submit” finishes the job; it does not, because without both the PE and Permittee acceptances and the paid fee, the review clock never starts.
Three Filled-Out Examples Using Real Scenarios
Below are three common fact patterns, each followed through the form from start to finish. Use them as templates, swapping in your own numbers.
Scenario 1: Marcus Bell installs a 38 MMBtu/hr natural gas boiler (Non-Major CPA-Fuel, BWP AQ 02)
| Form Section | What Marcus Enters |
|---|---|
| Step 1 Contact Information | Preparer: Marcus Bell; Permittee: plant owner; PE: firm engineer; Submitter: Marcus |
| Step 2 Facility and Owner | CleanPress Laundry, 22 Mill St, Lowell, MA 01852, selected from existing list |
| Step 3 SIC/NAICS | SIC 7211 (industrial laundries) |
| Step 3 Project Description | “Install one 38 MMBtu/hr natural gas boiler with low-NOx burner and FGR” |
| Step 3 Appendix A / PSD | No to Appendix A; No to PSD |
| Step 3 BACT | Low-NOx burner with flue gas recirculation as top-case BACT |
| Step 4 Documents | Boiler cut sheet, emission calculations, plot plan |
| Step 7 Certification | PE certifies with license number; Permittee accepts; fee $2,370 paid online |
Scenario 2: Janet Okafor installs a new coating line emitting 14 tpy VOC (Non-Major CPA-Process, BWP AQ 02)
| Form Section | What Janet Enters |
|---|---|
| Step 1 Contact Information | Preparer: Janet Okafor; Permittee: facility owner; PE: licensed engineer; Submitter: Janet |
| Step 2 Facility and Owner | Bay State Finishing, 14 Industrial Way, Fall River, MA 02720, entered as new |
| Step 3 SIC/NAICS | NAICS 332812 (coating and engraving) |
| Step 3 Project Description | “New solvent-based coating line, potential 14 tpy VOC, with RTO control” |
| Step 3 Process Emissions | 14 tons VOC per 12 months, above the 10-ton CPA-Process trigger |
| Step 3 BACT | Regenerative thermal oxidizer at 95% VOC destruction |
| Step 4 Documents | Spec sheets, BACT analysis, plot plan, and EJ Project Fact Sheet |
| Step 7 Certification | PE and Permittee certify; fee $2,370 paid by electronic check |
Scenario 3: Aisha Nguyen permits a new manufacturing source over 100 tpy near an EJ community (Major CPA-Process, BWP AQ 03)
| Form Section | What Aisha Enters |
|---|---|
| Step 1 Contact Information | Preparer: Aisha Nguyen (consultant); Permittee: company VP; PE: senior engineer; Submitter: Aisha |
| Step 2 Facility and Owner | Riverside Manufacturing, 5 Commerce Dr, Springfield, MA 01103, entered as new |
| Step 3 SIC/NAICS | NAICS 325199 (industrial organic chemicals) |
| Step 3 Project Description | “New process unit, potential 110 tpy VOC, major source, with carbon adsorption” |
| Step 3 PSD / Appendix A | Yes to PSD review and Yes to Appendix A nonattainment review |
| Step 3 Modeling | Ambient air quality modeling submitted to MassDEP Air and Climate Programs |
| Step 4 Documents | Modeling report, BACT/LAER analysis, emission offsets, and EJ Project Fact Sheet |
| Step 7 Certification | PE certifies with license; Permittee accepts; fee $24,305 paid online |
How to File the Completed Form
The standard and preferred channel is online through the EEA ePLACE Portal. You submit there at no charge for the portal itself, then pay the permit fee online by credit card or electronic check, each carrying a small handling fee, or by mailing a check to the address your regional office provides. Expect the formal review timeline to begin only after the fee clears or a fee exemption is verified, and you can track every stage under the “My Records” tab. Keep your Permit Application number and the PDF copy the system emails you as your proof of filing.
The base fees are set by tier: a Non-Major CPA (BWP AQ 02) is $2,370 and a Major CPA (BWP AQ 03) is $24,305, per the CPA instructions and FAQ. Review timelines for each permit type appear on the MassDEP Timely Action and Fees page, and the clock runs against those published targets.
The backup channel is paper. If you cannot file online, request a paper form from your MassDEP Regional Office and mail the completed form back to the attention of the BAW Regional Data Manager at that office’s address. Pay by mailed check, since the online payment options do not apply to paper filings. Keep a stamped copy or a certified-mail receipt as your proof of filing, because paper submissions lack the automatic ePLACE confirmation.
For both channels, the pre-application conference is the unofficial first step. It costs nothing, it is arranged through your regional office, and it can shave weeks off review by catching problems before you file. Keep your meeting notes, because they show good faith if a dispute over completeness ever arises.
What Happens After You File
Once the fee clears, MassDEP begins its review against the published timeline. You can watch the status move through the stages by logging into ePLACE and opening “My Records.” If the agency finds the application administratively or technically deficient, it contacts the Submitter, who is the only party able to reopen and edit the record, so keep that person available.
The agency may issue a draft Plan Approval for public comment, especially for Major sources and projects near Environmental Justice populations. During this window, neighbors and the public can weigh in, which is exactly why the EJ Fact Sheet matters so much up front. A well-prepared Fact Sheet can smooth this stage and head off objections.
Your final Plan Approval, once issued, stays in effect for the life of the approved emission units, even if ownership changes. It ends only when the project is substantially reconstructed or altered, or when MassDEP decides deeper emission reductions are needed, at which point a new approval is required. Remember the separate annual compliance assurance fee under 310 CMR 4.03; if you fail to pay it, your Plan Approval can be suspended or revoked.
Mistakes to Avoid When Filling Out the Form
- Starting construction before the written approval arrives, which exposes you to enforcement and penalties under 310 CMR 5.00.
- Picking the wrong tier (LPA vs. CPA, Major vs. Non-Major), which means a wrong fee and a rejected or misrouted application.
- Listing a PE or Permittee who lacks an ePLACE account, which freezes the certification chain so nothing can be submitted.
- Leaving non-asterisk fields blank, which makes the application technically incomplete even though the system let you advance.
- Entering the wrong SIC or NAICS code, which misroutes your file and can trigger the wrong review path.
- Creating a duplicate facility record, which scatters your permit history and confuses the reviewer.
- Answering “no” to PSD when the project actually triggers it, which forces a restart once the agency catches the missing PSD package.
- Submitting a Major CPA without the required ambient air quality modeling, which stops technical review cold.
- Forgetting the EJ Project Fact Sheet on a CPA-Process, which renders the submission incomplete on arrival.
- Claiming top-case BACT without attaching a BACT analysis, which guarantees a deficiency notice.
- Filing before the MEPA process is done, which blocks MassDEP from finishing technical review.
- Assuming “Submit” finishes the job, when the review clock never starts until both certifications post and the fee clears.
Do’s and Don’ts
Do:
- Schedule a pre-application conference, because it catches problems early and speeds review.
- Confirm every party holds an ePLACE account first, because the form routes by login.
- Gather all specs, calculations, and the Fact Sheet before opening the form, because gaps stall completeness.
- Attach more than the minimum documents, because the agency openly encourages a fuller record.
- Use the exact equipment ratings and stack data from manufacturer sheets, because reviewers verify them.
- Keep your Permit Application number and the emailed PDF, because they are your proof of filing.
Don’t:
- Don’t break ground before the written approval lands, because that invites penalties.
- Don’t guess your potential-to-emit, because it sets your tier and fee.
- Don’t ignore non-asterisk fields, because they still count toward completeness.
- Don’t name the prior owner after a sale, because the approval attaches to the current owner of record.
- Don’t let your PE’s license lapse mid-filing, because an expired license voids the certification.
- Don’t skip the EJ Fact Sheet on a Process application, because it is a required attachment.
Pros and Cons of Filing on Your Own vs. With a Consultant
| Filing Pro Se (In-House) | Filing With a Consultant/PE |
|---|---|
| Lower cost, because you avoid consultant fees | Higher cost, because you pay for expertise and time |
| Full control of your project narrative and schedule | Some hand-off of control, since the consultant drives the file |
| Direct learning of the rules for future filings | Faster learning curve, since the expert already knows the rules |
| Risk of errors, because the form and BACT analysis are technical | Fewer errors, because consultants file these often |
| Slower if you hit unfamiliar PSD or modeling steps | Faster on complex PSD, LAER, and modeling work |
| You still need a Massachusetts PE to certify regardless | The PE relationship is usually built into the consulting team |
Comparing the Two Main Application Tiers
| Non-Major CPA (BWP AQ 02) | Major CPA (BWP AQ 03) |
|---|---|
| Filing fee of $2,370 | Filing fee of $24,305 |
| For non-major sources under major thresholds | For major sources above federal/state major thresholds |
| Modeling sometimes required | Ambient air quality modeling required |
| Public comment in some cases | Public comment more common, especially near EJ areas |
| EJ Fact Sheet required for Process units | EJ Fact Sheet required for Process units |
| Same seven-step ePLACE process | Same seven-step ePLACE process, plus PSD/LAER add-ons |
FAQs
Do I need approval before I start construction?
Yes. You must hold a written Air Quality Plan Approval from MassDEP before you start construction or installation of any emission unit in your application, or you risk enforcement.
Is the application filed online?
Yes. The standard channel is the EEA ePLACE Portal, and every preparer, PE, and Permittee needs their own account to complete and certify the form.
Do I write the SIC code or the NAICS code in Step 3?
Yes, you provide one or the other. The form accepts either a Standard Industrial Classification code or a NAICS code to classify your facility’s industry.
Do I pick the existing facility or enter a new one in Step 2?
Yes, search the pre-loaded list first. If your site is not listed or is brand new, type the information in and do not select from the existing list.
Do I have to fill in fields without a red asterisk?
Yes, many are still required for completeness. Do not assume a field is optional just because it lacks a red asterisk, since the agency reviews the whole record.
Do I attach the EJ Fact Sheet inside the form?
Yes, for a CPA-Process. Attach it in the Documents step, select “Other” as the category, and type “Fact Sheet” in the description box.
Is a Massachusetts Professional Engineer required to certify?
Yes. The PE must review the application and certify with a separate statement that includes a current PE license number and expiration date.
Does hitting “Submit” finish my application?
No. Submission creates a Permit Application number, but the filing is not formal until both the PE and Permittee accept and the fee is paid.
Is the filing fee the same for Major and Non-Major applications?
No. A Non-Major CPA (BWP AQ 02) costs $2,370, while a Major CPA (BWP AQ 03) costs $24,305, set by your source’s tier.
Does the review clock start as soon as I file?
No. The review timeline begins only after the fee is paid or a requested fee exemption is verified, not at the moment you submit.
Do I need ambient air quality modeling?
Yes, for a Major CPA. MassDEP requires modeling with a Major application and may also require it for other projects depending on the source.
Does my Plan Approval expire on a set date?
No. It stays in effect for the life of the approved emission units, even through ownership changes, until the project is substantially altered or new reductions are required.
Do I still owe fees after approval?
Yes. A separate annual compliance assurance fee applies under 310 CMR 4.03, and failing to pay it can get your Plan Approval suspended or revoked.
Can I file on paper instead of online?
Yes, but only if you cannot file online. Request a paper form from your MassDEP Regional Office and mail it back to the BAW Regional Data Manager.
Related reading
- How to Fill Out the MassDEP Notice of Intent (WPA Form 3) — With Examples + FAQs
- How to Fill Out the MassDEP / EPA NPDES Construction Stormwater Permit (With Examples) + FAQs
- How to Fill Out the MassDEP / EPA NPDES Industrial Stormwater Notice of Intent (With Examples) + FAQs
- How to Fill Out the MassDEP Air Plan Approval Application (with Examples) + FAQs
- How to Fill Out MassDEP Notice of Intent (Wetlands) (w/Examples) + FAQs
- How to Fill Out the MassDEP NPDES Construction Stormwater Permit (With Examples) + FAQs
- How to Fill Out the Washington Ecology Water Quality Modification Permit + FAQs